Financial Number:
431113-1-52-01
Project Length: 0.36 miles
Project Limits: Underneath the 17th Street Causeway Bridge over the Intracoastal Waterway
Start Date: April 16, 2014
Completion Date: August 29, 2014
Contractor: Coastal Marine Construction, Inc.
Estimated Construction Cost: $2.6 million
Scope of Work: Project improvements included replacing power, control, and ground cables underneath the 17th Street Causeway Bridge to depths in accordance with U.S. Army Corp of Engineers requirements.