FDOT District Four - Broward County Header Image

Griffin Road from I-75 Interchange to Weston Road in Southwest Ranches/Weston/Davie

Financial Number: 415154-1-52-01

Project Length: 0.4 Miles

Project Limits: Griffin Road from I-75 Interchange to Weston Road.

Start Date: August 10, 2012

Completion Date: August 2013

Contractor: Williams Paving Inc.

Estimated Construction Cost: $2.1 million

Scope of Work
Project improvements included re-aligning the southbound entrance ramp, installing a new traffic signal on Griffin Road at the I-75 interchange, repaving all ramps and Griffin Road in the interchange, installing new highway lighting, installing new highways signs, installing new drainage and planting new landscaping.

Click here for upcoming lane closures

 

Project Photos

During Construction

Click to view enlarged version/details
During construction During construction During construction During construction
During construction During construction During construction During construction
During construction During construction

Post Construction

Click to view enlarged version/details
Post construction Post construction
 

Florida Department of Transportation
Florida Department of Transportation
Florida 511 Travel Info
FDOT District Four Youtube
SunGuide
Kids Zone
75 Express
95 Express