Financial Number:
433937-1-52-01
Project Length: 0.131 miles
Project Limits: The off-ramp from northbound I-95 to westbound Oakland Park Boulevard (Exit 31B)
Start Date: May 23, 2014
Completion Date: July 24, 2014
Contractor: Ranger Construction, Inc.
Estimated Construction Cost: $161,000
Scope of Work: Project improvements included adjusting the slope of the ramp to provide a more comfortable ride for motorists.