Financial Number: 427937-152-01, 427937-1-52-02, 427937-2-52-01, and 427937-2-52-02
Project Length: 9.797 miles
Project Limits: SR 7 from Commercial Boulevard to Broward / Palm Beach County Line in Tamarac, North Lauderdale, Fort Lauderdale, Margate, Coral Springs, Coconut Creek and Parkland
Start Date: September 10, 2017
Completion Date: May 7, 2020
Contractor: Community Asphalt Co.
Estimated Construction Cost: $14.2 million
Scope of Work: The improvements under this contract include removing old asphalt and resurfacing the roadway, upgrading pedestrian features including 10-foot sidewalks on both sides and detectable warning surfaces at crosswalks, installing overhead sign structures, upgrading signs and pavement markings to include a 7-foot bike lane in each direction, installing new bus shelters with bicycle racks, trash receptacles, and benches, upgrading drainage structures, upgrading signalization, including pedestrian signals and detectors and vehicle video detection, and upgrading lighting.
Updated May 21 2020 - Project Flyer - SR 7 Improvements
|