FDOT District Four - Broward County Header Image

SW 30th Avenue Widening Project in Dania Beach and Hollywood

Financial Number: 431757-1-52-01

Project Length: .55 miles

Project Limits: SW 30th Avenue from Griffin Road to SW 42nd Avenue

Start Date: October 24, 2016

Completion Date: May 6, 2017

Contractor: Weekley Asphalt Paving, Inc.

Estimated Construction Cost: $1.3 million


Scope of Work
The work under this contract consists of widening SW 30th Avenue from an urban 2-lane divided highway to an urban 4-lane divided highway, between Griffin Road and SW 45th Street. Improvements also include resurfacing with new signing and pavement markings between SW 45th Street and SW 42nd Street, new bike lanes, sidewalk and ADA ramp improvements, new street lighting, signal mast arm upgrades at Griffin Road, a new emergency signal at the Broward Sheriff’s Office substation and new landscaping.

PDF IconProject Flyer SW 30th Ave Widening Project

 

Click here for upcoming lane closures

 

Project Photos

Pre-Construction

     

During Construction

 

 

Florida Department of Transportation
Florida Department of Transportation
Florida 511 Travel Info
FDOT District Four Youtube
SunGuide
Kids Zone
75 Express
95 Express