FDOT District Four - Broward County Header Image

SW 4 Avenue at SW 28 Street Intersection Improvements Project in Fort Lauderdale

Financial Number: 437866-1-52-01

Project Length: .021 miles

Project Limits: SW 4 Avenue at SW 28 Street

Start Date: August 20, 2017

Completion Date: April 13, 2018

Contractor: Weekley Asphalt Paving, Inc.

Estimated Construction Cost: $741,586.31

Scope of Work:
Project improvements include installing new mast arm signals to replace the existing four-way stop signs, upgrading sidewalk and pedestrian curb ramps, removing old asphalt and resurfacing the intersection, minor widening along SW 28 Street to add left turn lanes, upgrading pavement markings and signs, and installing new drainage structures.

 

Click here for upcoming lane closures

 

Project Photos

Pre-Construction

     

During Construction

 

 

Florida Department of Transportation
Florida Department of Transportation
Florida 511 Travel Info
FDOT District Four Youtube
SunGuide
Kids Zone
75 Express
95 Express