Financial Number: 437866-1-52-01
Project Length: .021 miles
Project Limits: SW 4 Avenue at SW 28 Street
Start Date: August 20, 2017
Completion Date: April 13, 2018
Contractor: Weekley Asphalt Paving, Inc.
Estimated Construction Cost: $741,586.31
Scope of Work: Project improvements include installing new mast arm signals to replace the existing four-way stop signs, upgrading sidewalk and pedestrian curb ramps, removing old asphalt and resurfacing the intersection, minor widening along SW 28 Street to add left turn lanes, upgrading pavement markings and signs, and installing new drainage structures.
|