Financial Number:
424674-1-52-01
Project Length: 0.491 miles
Project Limits: Sheridan Street from east of the CSX Railroad to west of N 26th Avenue
Start Date: November 4, 2013
Completion Date: March 3, 2015
Contractor: Ranger Construction Industries, Inc.
Estimated Construction Cost: $4 million
Scope of Work: Project improvements included removing old asphalt and repaving Sheridan Street within the project limits, except within the I-95 interchange upgrading existing traffic signals to mast arms, upgrading pedestrian features including curbs and ramps to meet ADA standards, and improving drainage.