Financial Number:
430801-1-52-01; 430799-1-52-01; 432759-1-52-01
Project Length: 0.246 miles
Project Limits: SR 7/US 441 at Griffin Road, SR 7/US 441 at Seminole Way to Lucky Street, Griffin Road from SW 35th Avenue to SW 31st Avenue in Hollywood and Dania Beach
Start Date: August 4, 2014
Completion Date: May 7, 2015
Contractor: Weekley Asphalt Paving, Corp.
Estimated Construction Cost: $1.4 million
Scope of Work
The improvements under this contract included removing old asphalt and resurfacing the intersection, installing new mast arms, and installing new lighting at SR 7/US 441 and Griffin Road, installing new lighting and overhead signage from SR 7/US 441 from Seminole Way to Lucky Street, and installing new lighting on Griffin Road from SW 35th Avenue to SW 31st Street in Hollywood and Dania Beach.