Peters Road Improvements Project in the City of Plantation

Financial Number: 431698-1-52-01; 431698-1-52-01

Project Limits: Peters Road from Pine Island Road to SR 817 (University Drive)

Start Date: April 22, 2019

Completion Date: Fall 2019

Contractor: General Asphalt Company, Inc.

Estimated Construction Cost: $1,436,281

Scope of Work:
Project improvements include widening, resurfacing and restriping the roadway to accommodate 5-foot designated bike lanes with a 3-foot buffer and two 11-foot through lanes in each direction, installing curb and gutter along the median and outside lanes at the approaches to intersections and at bus stops, modifying pedestrian curb ramps to meet ADA requirements, relocating drainage structures, and upgrading lighting at University Drive.

 

Click here for upcoming lane closures

 

Project Photos

During Construction

   
 

Florida Department of Transportation
75 Express
95 Express
Florida 511 Travel Info
Twitter
SunGuide
Kids Zone
© 2014, Florida Department of Transportation District Four