Financial Number: 431657-1-52-01
Project Limits: SR 811 / NE 4 Avenue / Wilton Drive from Sunrise Boulevard to NE 26 Street
Start Date: August 13, 2018
Completion Date: Summer 2019
Contractor: Roadway Construction LLC
Estimated Construction Cost: approx. $3.3 million
Scope of Work: The improvements under this contract consist of removing old asphalt and resurfacing the roadway, upgrading signs and pavement markings, adding a buffered bike lane in each direction, widening sidewalks, upgrading pedestrian signals and modifying pedestrian curb ramps to meet ADA requirements, upgrading roadway and pedestrian lighting, installing new drainage structures and upgrading the existing drainage system.
Project Flyer - SR 811 NE 4 Avenue Wilton Drive Complete Streets