Financial Number: 437865-1-52-01
Project Length: .05 miles
Project Limits: SR 84 at SW 15 Avenue
Start Date: June 5, 2017
Completion Date: November 8, 2017
Contractor: I & C Earthmovers Corp.
Estimated Construction Cost: $281,110
Scope of Work: Project improvements included creating an opening in the existing median and widening the road toward the median to provide an exclusive u-turn lane from eastbound SR 84 to westbound SR 84, relocating drainage structures and a light pole in the median, removing trees in conflict with the new configuration, removing old asphalt and resurfacing the adjacent eastbound left turn lane, installing new signs and pavement markings, and upgrading signalization to accommodate the new configuration