Southern Boulevard / Lang Road Drainage Improvements

Financial Number: 429082-1-52-01

Project Length: 0.2 miles

Project Limits: Southern Boulevard from Lang Road to the C-51 Canal, and Lang Road from Southern Boulevard to Shannondale Road

Start Date: September 6, 2011

Estimated Completion Date: Early winter 2012

Contractor: CMA Corporation

Estimated Construction Cost: $229,589.21

Scope of Work:
Work consists of milling and resurfacing Lang Road from Southern Boulevard to Shannondale Road, installation of new drainage structures and storm pipes, and re-grading the existing retention pond along Southern Boulevard, just east of Lang Road, for conversion to a wet detention pond.

Click here for upcoming S.R. 809 lane closures

 

Project Photos

Pre-Construction

Pre-Construction Photo Pre-Construction Photo
Click to view an enlarged version Click to view an enlarged version
   

During Construction

During Construction Photo During Construction Photo
Click to view an enlarged version Click to view an enlarged version

Pond – West Side

Pond- East Side

 

Please click on a link below to view construction projects
in other areas of Palm Beach County:
  I-95 Palm Beach County I-95 Construction Palm Beach County Northern Palm Beach CountyNorthern Palm Beach County
  Southern Palm Beach CountySouthern Palm Beach County Western Palm Beach CountyWestern Palm Beach County
  Central Palm Beach CountyCentral Palm Beach County Bridges Palm Beach CountyBridge Construction Palm Beach County
Kids Zone
© 2012, Florida Department of Transportation District IV