Clint Moore Road Sidewalk Improvements

Financial Number: 4383881-52-01

Project Length: 0.41 miles

Project Limits: Clint Moore Road (south side only) from the El Rio Trail to NW 2nd Avenue. Project limits do not include the bridge over I-95 which will be fully reconstructed under the 95 Express Phase 3B-2 contract

Start Date: February 11, 2020

Completion Date: Summer 2020

Contractor: Heavy Civil, Inc.

Estimated Construction Cost: $291,936.26

Scope of Work:
Work includes construction of an 8-foot-wide paved asphalt sidewalk and additional safety enhancements – including pedestrian detectors, signals and an aluminum picket fence on the south side of Clint Moore Road, from the El Rio Trail to NW 2nd Avenue. Project limits do not include the bridge over I-95 which will be replaced under the 95 Express Phase 3B-2 contract.

PDF IconClint Moore Road Sidewalk Improvements Project Flyer

Click here for upcoming lane closures

 

 

Project Photos

Pre-Construction

Click to view enlarged version/details
 

Please click on a link below to view construction projects
in other areas of Palm Beach County:
  I-95 Palm Beach CountyI-95 Construction Palm Beach County Northern Palm Beach CountyNorthern Palm Beach County
  Southern Palm Beach CountySouthern Palm Beach County Western Palm Beach CountyWestern Palm Beach County
  Central Palm Beach CountyCentral Palm Beach County Bridges Palm Beach CountyBridge Construction Palm Beach County
Kids Zone
© 2014, Florida Department of Transportation District Four