Hamlin Boulevard Sidewalk Installation Project

Financial Number: 436899-1-52-01

Project Length: 0.71 miles

Project Limits: Hamlin Boulevard, from 190th Street N. to 180th Avenue N., in unincorporated Palm Beach County/Indian Trail Improvement District

Start Date: Feb. 27, 2020

Completion Date: May 29, 2020

Contractor: Hardrives, Inc.

Estimated Construction Cost: $304,597

Scope of Work:
Work included installation of a new 6-foot wide asphalt sidewalk on the south side of Hamlin Boulevard from 190th Street N. to 180th Avenue N., along with minor fencing and sign installation.

Click here for upcoming lane closures

 

 

Project Photos

Pre-Construction

Click to view enlarged version/details

During Construction

Click to view enlarged version/details
 

Please click on a link below to view construction projects
in other areas of Palm Beach County:
  I-95 Palm Beach CountyI-95 Construction Palm Beach County Northern Palm Beach CountyNorthern Palm Beach County
  Southern Palm Beach CountySouthern Palm Beach County Western Palm Beach CountyWestern Palm Beach County
  Central Palm Beach CountyCentral Palm Beach County Bridges Palm Beach CountyBridge Construction Palm Beach County
Florida Department of Transportation
Florida Department of Transportation
FDOT District Four Youtube
Kids Zone