I-95 Interchange Improvements at Atlantic Avenue

Financial Number: 434722-1-52-01

Project Length: 0.852 mile

Project Limits: SR 806 (Atlantic Avenue) from E4/El Rio Canal to NW 12th Avenue

Start Date: Fall 2018

Completion Date: Fall 2019

Contractor: Russell Engineering Inc.

Estimated Construction Cost: $5.2 million

Scope of Work:
Project improvements include widening of the northbound entrance ramp from Atlantic Avenue, creating a dedicated lane for I-95 northbound and southbound access from westbound Atlantic Avenue, construction of two turn lanes from westbound Atlantic Avenue; one to northbound Congress Avenue and one to southbound Congress Avenue, milling, resurfacing, construction of retaining walls, new watermain installation, drainage improvements, guardrail, sign structures, lighting, installation of fiber optic and ITS with CCTV video and ethernet, pavement markings for improved safety and visibility, realigned crosswalks for improved pedestrian safety, internally illuminated and electronic display signs, signalization, pedestrian detectors, and traffic monitoring sites. Pavement markings for bike lanes will be included throughout the project.

PDF IconI‐95 Interchange Improvements At Atlantic Avenue

Click here for upcoming lane closures

 

 

Project Photos

Pre-Construction

Click to view enlarged version/details

 

Please click on a link below to view construction projects
in other areas of Palm Beach County:
  I-95 Palm Beach County I-95 Construction Palm Beach County Northern Palm Beach CountyNorthern Palm Beach County
  Southern Palm Beach CountySouthern Palm Beach County Western Palm Beach CountyWestern Palm Beach County
  Central Palm Beach CountyCentral Palm Beach County Bridges Palm Beach CountyBridge Construction Palm Beach County
Kids Zone
© 2014, Florida Department of Transportation District Four