Treasure Coast Header Image

I-95 / State Road 9 Widening, from Indrio Road to the St. Lucie/Indian River County Line

Financial Number: 413047-1-52-01

Project Length: 4.069 miles

Project Limits: From just south of Indrio Rd./S.R. 614 to the St. Lucie/Indian River County Line

Start Date: August 15, 2011

Estimated Completion Date: Early 2013

Contractor: Dickerson Florida, Inc.

Estimated Construction Cost: $17.2 Million

Scope of Work
Adding one lane each direction in the existing median throughout along with milling/resurfacing of the existing pavement; widening I-95 bridge at Indrio Road; constructing a noise barrier wall at the Spanish Lakes community.

Click here for upcoming I-95 lane closures

 

Project Photos

Pre-Construction

Pre-Construction Photo Pre-Construction Photo
Click to view an enlarged version Click to view an enlarged version
   

During Construction

During Construction Photo During Construction Photo
Click to view an enlarged version Click to view an enlarged version

March 2012 - Indrio Rd. bridges
(north center).

March 2012 - Indrio Rd. bridges
(south center)

 

Please click on a link below to view construction projects
in other areas of Treasure Coast:
Martin County ProjectsMartin County St. Lucie CountySt. Lucie County Indian River CountyIndian River County
95 Widening Project
Kids Zone
© 2012, Florida Department of Transportation District IV