Financial Number: 413047-1-52-01
Project Length: 4.069 miles
Project Limits: From just south of Indrio Rd./S.R. 614 to the St. Lucie/Indian River County Line
Start Date: August 15, 2011
Estimated Completion Date: Early 2013
Contractor: Dickerson Florida, Inc.
Estimated Construction Cost: $17.2 Million
Scope of Work
Adding one lane each direction in the existing median throughout along with milling/resurfacing of the existing pavement; widening I-95 bridge at Indrio Road; constructing a noise barrier wall at the Spanish Lakes community.