Treasure Coast Header Image

State Road 70, from Bluefield Road to VPI Grove Road

Financial Number: 230262-2-52-01

Project Length: 5.87 miles

Project Limits: From 1.5 miles west of Bluefield Rd. to 1 mile east of VPI Grove Rd. (Okeechobee County/St. Lucie County Line)

Start Date: January 31, 2011

Estimated Completion Date: Summer 2014

Contractor: Guettler Brothers Construction, LLC

Estimated Construction Cost: $18.8 Million

Scope of Work
Project includes widening from two-lane undivided to a four-lane divided rural highway, with 64 feet wide median, outside and inside shoulders, a 12-feet wide shared-use pathway, removal of existing drainage system, and the formation of ditch and berm on either side.

Click here for upcoming S.R. 70 lane closures

 

Project Photos

Pre-Construction

Pre-Construction Photo Pre-Construction Photo
Click to view an enlarged version Click to view an enlarged version
   

During Construction

During Construction Photo During Construction Photo
Click to view an enlarged version Click to view an enlarged version
Clearing and Grubbing Special Detour I (Phase I). Clearing and Grubbing.
During Construction Photo During Construction Photo
Click to view an enlarged version Click to view an enlarged version
  S-343C to S-345
During Construction Photo During Construction Photo
Click to view an enlarged version Click to view an enlarged version
Finish grading north slope March 2012
During Construction Photo  
Click to view an enlarged version  
March 2012  
 

Please click on a link below to view construction projects
in other areas of Treasure Coast: