Financial Number: 422956-1-52-01
Project Length: 3.589 miles
Project Limits: From east of Jenkins Rd. to US-1 / S.R. 5
Start Date: August 31, 2011
Estimated Completion Date: Summer 2012
Contractor: Community Asphalt Corporation
Estimated Construction Cost: $4.12 Million
Scope of Work
Resurfacing
Click here for upcoming S.R. 70 lane closures |