State Road 70, from Summerlin Road to 1.6 Miles East of VPI Grove Road

Financial Number: 230262-3-52-01

Project Length: 4.3 miles

Project Limits: From .5 miles east of Summerlin Rd. westerly to 1.6 miles east of VPI Grove Rd.

Start Date: September 8, 2009

Estimated Completion Date: Summer 2012

Contractor: J. W. Cheatham, LLC

Estimated Construction Cost: $12.4 Million

Scope of Work
Reconstruction from a two-lane divided highway to a four-lane undivided highway including drainage, driveway, signing and pavement marking improvements, and the construction of a 12’ wide shared-use pathway.  

Click here for upcoming S.R. 70 lane closures

 

Project Photos

Pre-Construction

Pre-Construction Photo Pre-Construction Photo
Click to view an enlarged version Click to view an enlarged version
   

During Construction

During Construction Photo During Construction Photo
Click to view an enlarged version Click to view an enlarged version
J.W. Cheatham paving. Traffic Control Products preparing to install temporary barrier wall.
   
During Construction Photo During Construction Photo
Click to view an enlarged version Click to view an enlarged version
Contractor and CEI project personnel coring mainline base rock.

Ocean Breeze installing Rip Rap Fabric Form.
(end walls)

During Construction Photo During Construction Photo
Click to view an enlarged version Click to view an enlarged version

March 2012 -  Paving 2nd lift of structural asphalt

March 2012 - Cleaning the cross drain in preparation for the pending final pipe inspection

   
 

Please click on a link below to view construction projects
in other areas of Treasure Coast:
Martin County ProjectsMartin County St. Lucie CountySt. Lucie County Indian River CountyIndian River County
95 Widening Project
Kids Zone
© 2012, Florida Department of Transportation District IV