State Road 710 / Warfield Boulevard from East of Kanner Highway (State Road 76) to the Martin / Palm Beach County Line

Financial Number: 432705-1-52-01

Project Length: 5.572 miles

Project Limits: From East of Kanner Highway (State Road 76) to the Martin / Palm Beach County Line

Start Date: February 27, 2017

Estimated Completion Date: Spring 2020

Contractor:  Ranger Construction Industries, Inc.

Estimated Construction Cost: $27,999,900

Scope of Work:
The improvements under this contract consist of reconstructing State Road 710 to a 4-lane divided roadway with a 40-foot sodded median, concrete pavement, installing a new drainage system, and constructing a new wildlife crossing west of the Martin / Palm Beach County Line.

Click here for upcoming lane closures

 

 

 

Project Photos

Pre-Construction

Click to view enlarged version/details
Pre-construction Pre-construction Pre-construction Pre-construction

During-Construction

Click to view enlarged version/details
Construction Photo Construction Photo Construction Photo Construction Photo
Construction Photo Construction Photo Construction Photo Construction Photo
Construction Photo Construction Photo Construction Photo Construction Photo
Construction Photo Construction Photo Construction Photo Construction Photo
Construction Photo Construction Photo Construction Photo Construction Photo
Construction Photo Construction Photo
       
 

Please click on a link below to view construction projects
in other areas of Treasure Coast:
Martin County ProjectsMartin County St. Lucie CountySt. Lucie County Indian River CountyIndian River County
Florida Department of Transportation
Kids Zone
© 2014, Florida Department of Transportation District Four