McCarty Road North Bridge Replacement Project over Ten Mile Creek

Financial Number: 434360-1-52-01

Project Length: 0.12 miles

Project Limits: From Twin Creeks Drive north for 0.12 miles

Start Date: July 31, 2017

Estimated Completion Date: Spring 2018

Contractor: Morrison-Cobalt JV

Estimated Construction Cost: $1,472,241.75

Scope of Work
Work on this project includes: replacing the McCarty Road Bridge over Ten-Mile Creek, raising the bridge approximately 2 feet above the existing bridge elevation to better accommodate flood creek water elevations; replacing both approach slabs; roadway reconstruction and widening immediately north and south of the new bridge; drainage improvements including new inlets and installation of a French-drain system and providing slope protection/channel lining below the bridge to prevent erosion; and installing signing and pavement markings. The new bridge configuration will be a two-lane undivided road with 12’ lanes, outside shoulders, and a sidewalk on the east side of the bridge.

Click here for upcoming lane closures

 

Project Photos

Pre-Construction

Click to view enlarged version/details
   
       


During Construction


Please click on a link below to view construction projects
in other areas of Treasure Coast:
Martin County ProjectsMartin County St. Lucie CountySt. Lucie County Indian River CountyIndian River County
Florida Department of Transportation
Kids Zone
© 2014, Florida Department of Transportation District Four