Savannas Preserve State Park SUN Trail Improvements Project

Financial Number: 439999-2-52-01

Project Limits: 6.8 Miles

Project Length: From Walton Road to Kitterman Road

Start Date: July 26, 2023

Completion Date: Summer 2025

Contractor: Ferreira Construction Co., Inc.

Estimated Construction Cost: $10.6 million


Scope of Work:

Project improvements consist of constructing approximately 6.8 miles of accessible multi-use trail featuring a 10-foot wide multi-use trail with boardwalk sections.

Point of Contact:

Para información y preguntas en Español, por favor llame al (954) 777-4302.

Documents:

PDF IconVPM Savannas SUN Trail - FINAL

PDF IconSUN Trail Improvements Project Meeting Invitation Flyer

 

Project Photos

Pre-Construction

Click to view enlarged version/details

During Construction

Click to view enlarged version/details
The contractor forming for concrete trail, Feb. 2024 The contractor grading and stabilizing for the concrete trail, Feb. 2024 The contractor finishing the concrete trail, Mar. 2024 The contractor grading and stabilizing for the concrete trail, Mar. 2024





Please click on a link below to view construction projects
in other areas of Treasure Coast:
Martin County ProjectsMartin County St. Lucie CountySt. Lucie County Indian River CountyIndian River County
Florida Department of Transportation
Florida Department of Transportation
Florida 511 Travel Info
FDOT District Four Youtube
SunGuide
Kids Zone