U.S. 1 Resurfacing Project

Financial Number: 428728-1-52-01

Project Length: 2.362 miles

Project Limits: From north of Midway Road to north of Edwards Road

Start Date: February 5, 2018

Completion Date: Spring 2019

Contractor: Horizon Contractors, Inc.

Estimated Construction Cost: $6,194,381.38

Scope of Work:
This project includes removing old asphalt and resurfacing the existing five-lane roadway, adding sidewalks along both sides of the roadway, re-striping the existing roadway, upgrading signalization, drainage improvements, modifying the southbound right turn lane into the bus bay south of Market Avenue, upgrading the northbound bus bay south of Farmers Market Road, and adding a southbound bus bay south of Farmers Market Road.

Click here for upcoming lane closures

 

 

Project Photos

Pre-Construction

Click to view enlarged version/details
Pre-construction Pre-construction Pre-construction Pre-construction
Pre-construction

Please click on a link below to view construction projects
in other areas of Treasure Coast:
Martin County ProjectsMartin County St. Lucie CountySt. Lucie County Indian River CountyIndian River County
Florida Department of Transportation
Kids Zone
© 2014, Florida Department of Transportation District Four