Roosevelt Bridge/US 1/State Road 5 Restriping and Pedestrian Improvements Project from SW Joan Jefferson Way to NW Wright Boulevard

Financial Number: 438345-1-52-01

Project Length: 2.529 miles

Project Limits: From SW Joan Jefferson Way to NW Wright Boulevard

Start Date: April 16, 2020

Estimated Completion Date: Summer 2020

Contractor: J.W. Cheatham, LLC



Estimated Construction Cost: $1,005,699

Scope of WorkThe improvements on this project include: removing and replacing the existing pavement markings on the Roosevelt Bridge to accommodate 7’ buffered bike lanes; milling and resurfacing and restriping of the bridge approaches; upgrading curb ramps to meet the Americans with Disabilities Act (ADA); replacing existing crosswalks with high emphasis pavement markings; and replacing existing roadway signs along US 1.

Click here for upcoming lane closures

 

Project Photos

Pre-Construction

Click to view enlarged version/details
Pre-construction

 

 

 

Please click on a link below to view construction projects
in other areas of Treasure Coast:
Martin County ProjectsMartin County St. Lucie CountySt. Lucie County Indian River CountyIndian River County
Florida Department of Transportation
Kids Zone
© 2014, Florida Department of Transportation District Four