95 Express Phase 3A-2 from North of Commercial Boulevard to South of SW 10th Street

Financial Number: 433108-5-52-01

Project Length: 7.3 miles

Project Limits: I-95 from north of Commercial Boulevard to south of SW 10th Street

Start Date: January 8, 2016

Completion Date: October 3, 2019

Contractor: Prince Contracting LLC

Estimated Construction Cost: $154 million

Scope of Work:
Project improvements will include extending the existing express lanes north from just north of Commercial Boulevard to just south of SW 10th Street in Broward County. One lane will be added and the High Occupancy Vehicle (HOV) lane will be converted to create two express lanes in each direction. This project includes ramp signalization from Cypress Creek Road to Sample Road. Other work includes: installing Intelligent Transportation System (ITS) and tolling equipment; widening bridges; and installing noise barrier walls at locations along I-95 Northbound between Atlantic Boulevard and Sample Road, and along I-95 Southbound north of Sample Road

PDF Icon95 Express 3A-2 Fact Sheet Fall 2019

PDF Icon95 Express Frequently Asked Questions

PDF Icon95 Express Guide to Ramp Signaling in Broward and Palm Beach Counties

 

Click here for upcoming lane closures

 

 

Project Photos

Pre-Construction

During Construction

 
 
 
 
 
 
 



Please click on a link below to view construction projects
in other areas of Broward County:
I-95 Palm Beach CountyInterstates Northern Palm Beach CountyNortheast Western Palm Beach CountyNorthwest
I-95 Palm Beach CountySoutheast Northern Palm Beach CountySouthwest
Florida Department of Transportation
Florida Department of Transportation
Florida 511 Travel Info
FDOT District Four Youtube
SunGuide
Kids Zone
75 Express
95 Express