Financial Number: 441774-1-52-01
Project Length: 385 feet
Project Limits: SR 817/University Drive and Johnson Street
Start Date: January 25, 2022
Completion Date: Summer 2022
Contractor: Weekley Asphalt Paving, Inc.
Estimated Construction Cost: $436,772.47
Scope of Work: Improvements include upgrading 2 existing light poles to LED, installing 3 new light poles
Milling and resurfacing at the Intersection, reconstructing medians on SR 817/University Drive south of Johnson Street to NW 11th Street, replacing signing and pavement markings.
Document:
SR 25/US 27 Lighting Improvements Project in Broward County
|