Financial Number: 439759-1-52-01
Project Length: 0.154 miles
Project Limits: State Road 9/I-95 Northbound Off-Ramp at Belvedere Road in Palm Beach County and the City of West Palm Beach
Virtual Public Meeting:
Projected Letting: July 27, 2022
Start Date: Fall 2022
Completion Date: Winter 2023
Estimated Construction Cost: $2.2 million
Scope of Work:
- Add a second right-turn lane on the northbound off-ramp at Belvedere Road and provide 10-ft paved shoulders
- Widen, mill and resurface the existing SR 9/I-95 northbound off-ramp and
eastbound Belvedere Road
- Provide new mast arm assemblies and pedestrian countdown signals
- Implement Wrong Way Driving Countermeasure System
- Upgrade signing and pavement markings
- Upgrade lighting at the intersection
- Minor modifications to drainage, sidewalk, and curb and gutter
Construction Impacts:
- Work will be completed in phases to minimize construction impacts
- Single lane closures will be required during construction along eastbound Belvedere Road and the I-95 northbound off-ramp to Belvedere Road
- Off-ramp access will be maintained throughout construction
Contact Information:
Documents
Comment Form I-95 NB Off-Ramp at Belvedere Road
Belvedere NB Ramp Public Workshop Presentation
Virtual Public Meeting Scheduled for SR 9 / I-95 Northbound Off-Ramp at Belvedere Road Project
State Road 9 / I-95 Northbound Off-ramp At Belvedere Road Improvement Project
|