Financial Number: 446097-1-52-01
Project Length: 1.291 miles
Project Limits: SR 710/ Beeline Highway from east of Pratt & Whitney main entrance to east of the CSX railroad tracks
Virtual Public Workshop: N/A
Projected Letting: September 2022
Start Date: Winter 2022
Completion Date: Winter 2023
Estimated Construction Cost: $2.6 Million
Scope of Work:
- Add flashing beacons to the signal ahead warning signs around curves to enhance visibility.
- Repave roadway in order to extend the pavement life.
- New highway signing and pavement markings (including rumble strips).
- Add internally illuminated street name signs at the signalized intersections.
- Upgrade lighting by replacing the existing High-Pressure Sodium (HPS) luminaires with Light-Emitting Diode (LED) luminaires.
Construction Impacts:
- Work will be done in phases to reduce the effects of construction on the community.
- Occasional single lane closures during construction.
- Two-way traffic and access to all property will be maintained at all times.
Contact Information: