Financial Number: 441775-1-52-01
Project Length: 0.400 Miles
Project Limits: State Road (SR) 805/Dixie Highway from Eastbound SR 802/Lake Avenue to Westbound SR 802/Lucerne Avenue
Start Date: Spring 2022
Completion Date: Fall 2022
Estimated Construction Cost: $1 million
Scope of Work:
- Installing new traffic signals at the intersections of SR 802/Lake Avenue and SR 802/Lucerne Avenue
- Installing a flashing yellow arrow for all left turns at the intersections
- Upgrading pedestrian signal features
- Reconstruction of sidewalk affected by mast arm and light pole installation
- Upgrading lighting at the intersections
Construction Impacts:
- Construction will be allowed on one corner at the time
- No full roadway closures are anticipated
- All lane closures will occur during non-peak hours
- Access to businesses and residents will be maintained at all times during construction
Contact Information:
Construction Impacts:
Lighting And Signal Improvement Project Flyer
|