Treasure Coast Header Image

SR-5/US-1 Resurfacing Project

Financial Number: 446110-1-52-01

Project Length: 5.042 Miles

Project Limits: SR-5/US-1 from SE Contractors Way to north of SR-732/Jensen Beach Boulevard excluding SW Joan Jefferson Way to NW Wright Boulevard (no work on the Roosevelt Bridge).

Construction Start Date: July 25, 2022

Start Date: June 2023

Completion Date: Fall 2024

Contractor: OHLA-USA, Inc.

Estimated Construction Cost: $12 million

Scope of Work: The project improvements on SR-5/US-1 consist of milling and resurfacing the existing roadway excluding SW Joan Jefferson Way to NW Wright Boulevard (no work on the Roosevelt Bridge), drainage improvements, constructing sidewalks to fill in missing gaps, upgrading curb ramps to meet Americans with Disabilities Act (ADA) standards, installing pedestrian pushbutton detectors at signalized intersections, and upgrading pavement markings and lighting signalized intersections.

Point of Contact:

"Para información y preguntas en Español, por favor llame al (954) 777-4302."

Documents:

PDF IconVPM SR 5 Resurfacing Project Presentation - Final

 

Project Photos

Pre-Construction

Click to view enlarged version/details
Pre-construction Pre-construction Pre-construction Pre-construction

During Construction

Click to view enlarged version/details
Pre-construction Pre-construction Pre-construction Pre-construction
Pre-construction Pre-construction Pre-construction Pre-construction
Pre-construction Concrete removal for proposed sidewalk at northbound US facing northwest, Mar. 2023
Forming sidewalk at Ocean Boulevard looking west, Mar. 2023 Finishing the sidewalk at the SE corner of Johnson Ave and US 1, looking north, April 2024 Construction digging to install ped pole base at the SE Corner of Wright Boulevard Intersection, lookin south from northbound US 1, April 2024 Paving the intersection of US 1 and Jensen Beach Boulevard lookin south, May 2024
Finishing sidewalk at the NE Corner of Johnson Ave, May 2024 Paving northbound US 1, facing north, June 2024 Subcontractor striping northbound on US 1 at the Palm City Road intersection, June 2024 Looking south from northbound of US 1. Contractor performing friction course paving operation at northbound of US 1, before NW Jensen Beach Blvd., July 2024
Looking north from northbound of US 1. Contractor grading swale northbound of US 1, before NW Britt Rd Intersection, July 2024Paving northbound US 1 looking northwest before the Johnson Ave intersection, Aug. 2024

 

 

 

Please click on a link below to view construction projects
in other areas of Treasure Coast:
Martin County ProjectsMartin County St. Lucie CountySt. Lucie County Indian River CountyIndian River County

Florida Department of Transportation
Florida Department of Transportation
Florida 511 Travel Info
FDOT District Four Youtube
SunGuide
Kids Zone