Financial Number: 440473-1-52-01
Project Length: 1.842
Project Limits: State Road (SR) 732/Jensen Beach Causeway from NE Indian River Drive to SR A1A
Public Meeting: Tuesday, April 12, 2022 5:30 p.m.
The Public meeting will be offered in two different formats: virtual and in-person.
Start Date: Spring 2023
Completion Date: Spring 2024
Estimated Construction Cost: $2.8 million
Scope of Work:
- Repave the existing roadway
- Replace damaged sidewalk
- Upgrade pedestrian curb cut ramps
- Upgrade signing and markings to provide buffered bike lanes
- Replace existing bridge lighting and decorative pier lights
Construction Impacts:
- Work will be done in phases to reduce the inconvenience to the community
- Shoulder closures will occur for lighting construction
- Bicycle traffic will be maintained on the road using shared lane markings
- Partial detours (one direction at a time) will occur during non-peak hours for a restricted number of days to minimize impacts on traffic
- Pedestrian detours will occur, however, one side of the sidewalk will remain open at all times
- Access to businesses, residences, and the park will be maintained at all times during construction
- Nighttime work is expected for the repaving operations
Click here for upcoming lane closures
|