FDOT District Four - Broward County Header Image

Lighting Improvements Project SR A1A/SE 17th Street/Seabreeze Boulevard from Miami Road to Harbor Drive; SR A1A from Sebastian Street to SE 13th Street; SR 838/Sunrise Boulevard from Magic Leap entrance to Andrews Avenue

Financial Number: 440072-1-52-01; 440073-1-52-01; 440074-1-52-01

Project Length: Approximately 13-miles

Project Limits: SR A1A/SE 17th Street/Seabreeze Boulevard from Miami Road to Harbor Drive; SR A1A from Sebastian Street to SE 13th Street; SR 838/Sunrise Boulevard from Magic Leap entrance to Andrews Avenue

Start Date: November 21, 2019

Completion Date: Winter 2020

Contractor: PowerCore, Inc.

Estimated Construction Cost: $1,550,074

Scope of Work:
Work consists of upgrading existing roadway lighting with new LED fixtures to provide efficient light distribution, save energy and reduce maintenance costs. Improvements will also include new LED lighting at 8 intersections along SR A1A from Miami Road to Harbor Drive, 28 intersections along A1A from Sebastian Street to SE 13th Street and 15 intersections along Sunrise Boulevard.

 

Click here for upcoming lane closures

 

Project Photos

Pre-Construction

   

During Construction

 

 

 

Florida Department of Transportation
75 Express
95 Express
Florida 511 Travel Info
Twitter
SunGuide
Kids Zone
© 2014, Florida Department of Transportation District Four