Financial Number: 431665-1-52-01 and 431665-1-52-02
Project Length: 3.041 miles
Project Limits: NW 19 Street from SR 7 / US 441 to SR 845 / Powerline Road
Start Date: August 25, 2018
Completion Date: Spring 2019
Contractor: Weekley Asphalt Paving, Inc.
Estimated Construction Cost: $1.3 million
Scope of Work: The improvements under this contract include widening, resurfacing and restriping the roadway to accommodate the following configuration from SR 7 to NW 31 Avenue: 4-foot designated bike lanes and two 10-foot through lanes in each direction separated by a continuous two-way left turn lane in the center of the roadway, upgrading pedestrian signals and modifying pedestrian curb ramps and sidewalks to meet ADA requirements from SR 7 to NW 31 Avenue, relocating existing drainage system to accommodate widening areas from SR 7 to NW 31 Avenue, and upgrading lighting at SR 7 and Powerline Road intersections.
Project Flyer - NW 19 Street Improvements Project
|