FDOT District Four - Broward County Header Image

NW 19 Street Bike Lanes and Rehabilitation Project in Lauderdale Lakes, Lauderhill, and Fort Lauderdale

Financial Number: 431665-1-52-01 and 431665-1-52-02

Project Length: 3.041 miles

Project Limits: NW 19 Street from SR 7 / US 441 to SR 845 / Powerline Road

Start Date: August 25, 2018

Completion Date: Spring 2019

Contractor: Weekley Asphalt Paving, Inc.

Estimated Construction Cost: $1.3 million

Scope of Work:
The improvements under this contract include widening, resurfacing and restriping the roadway to accommodate the following configuration from SR 7 to NW 31 Avenue: 4-foot designated bike lanes and two 10-foot through lanes in each direction separated by a continuous two-way left turn lane in the center of the roadway, upgrading pedestrian signals and modifying pedestrian curb ramps and sidewalks to meet ADA requirements from SR 7 to NW 31 Avenue, relocating existing drainage system to accommodate widening areas from SR 7 to NW 31 Avenue, and upgrading lighting at SR 7 and Powerline Road intersections.

PDF IconProject Flyer - NW 19 Street Improvements Project

 

Click here for upcoming lane closures

 

Project Photos

Pre-Construction

     

During Construction

 

 

Florida Department of Transportation
Florida Department of Transportation
Florida 511 Travel Info
FDOT District Four Youtube
SunGuide
Kids Zone
75 Express
95 Express