Financial Number: 431752-5-52-01
Project Length: 1.076 miles
Project Limits: The project limits are on Southwest Port St. Lucie Boulevard from south of Southwest Paar Drive to south of Southwest Alcantarra Boulevard in the City of Port St. Lucie.
Virtual Public Meeting: Thursday, August 28, 2025, from 5:00 p.m. to 6:00 p.m. A brief presentation followed by questions and comments from the public will be held from 5:00 p.m. to 5:30 p.m. and again from 5:30 p.m. to 6:00 p.m. Please use the following link to register: https://bit.ly/PSLBLVD . You may also call +1 (562) 247-8321, Access Code: 791-226-075.
In-Person Construction Open House: Thursday, August 28, 2025, from 6:00 p.m. to 7:00 p.m. at the City of Port St. Lucie Municipal Complex, located at 121 SW Port St. Lucie Boulevard, Building A, First Floor, Port St. Lucie, FL 34984.
Start Date: September 2025
Completion Date: Summer 2028
Contractor: Roadway Construction, LLC
Estimated Construction Cost: $25,577,357
Scope of Work: Coming Soon
Point of Contact:
Para información y preguntas en Español, por favor llame al (954) 777-4302.
|