Financial Number: 446168-1-52-01
Project Length: 0.646 miles
Project Limits: SR 68/Orange Avenue from SR 713/Kings Highway to East of SR 9/I-95 SB Ramp
Letting Date: Summer 2028
Start Date: Fall 2028
Completion Date: Fall 2029
Estimated Construction Cost: $6 M
Project Improvements:
- Realign eastbound (EB) SR 68 to I-95 southbound (SB) on-ramp.
- Add an additional WB right turn lane at WB approach to SR 713/Kings Highway.
- Repave the existing roadway along SR 68 from SR 713/Kings Highway to I-95 SB on-ramp intersection.
- Relocate/adjust impacted drainage structures and regrade swales impacted by the roadway improvements.
- Install new signage and pavement markings including two new overhead sign structures.
- Install new pedestrian signalization features.
- Lighting upgrades along SR 68 and I-95 SB on-ramp.
- Relocate trees impacted by the roadway improvements.
Construction Impacts:
- Stakeholders in the area include businesses, schools, a hospital and an airport.
- There are few residents in the area, and the impact should be minor.