| Financial Number: 447555-1-52-01, 447555-2-52-01, 453333-3-52-01, 453333-2-52-01, 453333-1-52-01, 453333-4-52-01 Project Length: 17.745 miles 
  FM 447555-1-52-01: 0.485 milesFM 447555-2-52-01: 0.356 milesFM 453333-3-52-01: 0.315 milesFM 453333-2-52-01: 9.812 milesFM 453333-1-52-01: 5.939 milesFM 453333-4-52-01: 0.838 miles Project Limits:  
  FM 447555-1-52-01: SR-710/SW WARFIELD BOULEVARD AT CR-714/SW MARTIN HIGHWAYFM 447555-2-52-01: SR-710/SW WARFIELD BLVD FR W OF SE 126 BLVD TO OKEECHOBEE/MARTIN CO LINEFM 453333-3-52-01: SR-710/SW WARFIELD BLVD FR W OF SE 126 BLVD TO OKEECHOBEE/MARTIN CO LINEFM 453333-2-52-01: SR-710 FROM MARTIN/OKEECHOBEE CO LINE TO FPL POWER PLANT ACCESS ROADFM 453333-1-52-01: SR-710/SW WARFIELD BLVD FR FPL ACCESS RD TO SW ALLAPATTAH ROADFM 453333-4-52-01: SR-710/SW WARFIELD BLVD FR SW ALLAPATTAH ROAD TO SW VAN BUREN AVE Virtual Public Workshop: To Be DeterminedLink to registration page (to be determined) Projected Letting:  
  FM 447555-1-52-01: 7/25/2029FM 447555-2-52-01: 7/25/2029FM 453333-3-52-01: 7/25/2029FM 453333-2-52-01: Anticipated November 2030FM 453333-1-52-01: Anticipated November 2030FM 453333-4-52-01: 7/25/2029 Start Date: To Be Determined Completion Date: To Be Determined Estimated Construction Cost: $221.3 M 
  FM 447555-1-52-01: 5.1MFM 447555-2-52-01: 13.1MFM 453333-3-52-01: 2.3MFM 453333-2-52-01: 126.2MFM 453333-1-52-01: 62.5MFM 453333-4-52-01: 12.1M Scope of Work:FM 447555-1-52-01 and FM 447555-2-52-01 
FM 453333-3-52-01Realignment of CR-714 to SE 126 BlvdNew Signalization at SE 126 Blvd intersection 
  FM 453333-2-52-01 and FM 453333-1-52-01SR-710 roadway widening with turn lanes at SE 126 Blvd intersectionNew 
FM 453333-4-52-01SR-710 conversion from 2 lane undivided roadway to a raised 4 lanes divided roadway with a medianSeparating shared ditches by providing independent roadway drainage ditches and irrigation ditches Shared Use Path along the northeast side of the road for pedestrian and cyclist useNew Signage and Pavement MarkingsOverhead Utility Relocation 
Intersection improvements at SW Allapatah Rd. and Indianwood Dr. and new flashing signal at Martin County Fire Rescue - Station 24 east of SW Allapattah Rd.Shared Use Path along both sides of the Indiantown limits of SR-710Drainage improvements along the Indiantown limits of SR-710 Construction Impacts: To be Determined Documents:   Contact Information:  Para información y preguntas en Español, por favor llame al (954) 777-4302. |