Financial Number:
428727-1-52-01
Project Length: 0.906 miles
Project Limits: A1A from County Line Road to Seacrest Parkway
Start Date: October 13, 2014
Completion Date: January 11, 2016
Contractor: Weekly Asphalt Paving Inc.
Estimated Construction Cost: $2.7 million
Scope of Work: The improvements under this project included removing old asphalt and repaving with new asphalt within the project limits, upgrading signalization, installing stamped asphalt at pedestrian crosswalks, installing pedestrian countdown timers, installing "Share the Road" signage and pavement markings, and installing new mast arms.