Financial Number:
403984-1-52-01
Project Length: 0.04 Miles
Project Limits: S.R. 862 from a point west of S.R.5 (U.S.1) to a point east of McIntosh Road.
Start Date: July 2011
Estimated Completion Date: first quarter of 2015
Contractor: Astaldi Construction Corporation
Estimated Construction Cost: $42.5 Million
Scope of Work
A new overpass is being built over Eller Drive and the Port Everglades Railroad. The project includes reconstruction of several ramps in the I-595/US 1/Eller Drive interchange, reconstruction of the Eller Drive intersections at NE 7th Avenue, NE 14th Avenue and McIntosh Road, installation of new railroad tracks and crossing signals, drainage retention ponds, moving utilities out of the construction path, concrete pavement roadway construction, highway lighting system, landscaping and irrigation.