Financial Number:
427012-2-52-01
Project Length: 0.159 miles
Project Limits: Flamingo Road at SW 8th Street
Start Date: May 5, 2014
Completion Date: August 22, 2014
Contractor: Weekley Asphalt, Inc.
Estimated Construction Cost: $539,488.83
Scope of Work: Project improvements included installing a new traffic signal and lighting. Widening of SW 8th Street, widening of the right turn bay on Flamingo Road to accommodate new bike keyhole and modifications/ improvements upon existing pedestrian and drainage facilities in the town of Davie.
Click here for upcoming lane closures |