Financial Number: 433977-1-52-01
Project Length: .8 miles
Project Limits: Las Olas Boulevard from Isle of Capri Drive to west of the Intracoastal
Start Date: June 18, 2017
Completion Date: July 20, 2017
Contractor: Roadway Construction LLC
Estimated Construction Cost: $280,209.44
Scope of Work: The improvements under this contract include cleaning drainage pipes and installing liners as needed and installing flap gate valves at eleven locations along Las Olas Boulevard from Isle of Capri Drive to west of the Intracoastal Waterway to keep water from flowing out of the inlets and onto the roadway.
Project Flyer - Las Olas Blvd Drainage Improvements Project
|