Powerline Road Improvements Project in Deerfield Beach

Financial Number: 430605-1-52-01

Project Length: 1.36 milesĀ 

Project Limits: Powerline Road from north of West Drive to the Broward / Palm Beach County Line

Start Date: October 20, 2014

Completion Date: September 28, 2015

Contractor: Weekly Asphalt Paving Inc.

Estimated Construction Cost: $3,035,505.98

Scope of Work: Project improvements included widening Powerline Road from north of West Drive to the Broward / Palm Beach County Line to accommodate bike lanes and shoulders from north of West Drive to the Broward / Palm Beach County Line, removed old asphalt and resurfacing the roadway, upgrading curbs and ramps to meet ADA standards, installed new pavement markings, installing new street signs, installed pedestrian countdown timers, improved lighting on the west side of Powerline Road just north of Hillsboro Boulevard.

Click here for upcoming lane closures

 

Project Photos

Pre-Construction

Click to view enlarged version/details
Pre-construction Photo

During-Construction

During construction Photo During-construction Photo During-construction Photo During-construction Photo
During-construction Photo      
 

Florida Department of Transportation
Florida Department of Transportation
Florida 511 Travel Info
FDOT District Four Youtube
SunGuide
Kids Zone
75 Express
95 Express