State Road (SR) 844/NE 14th Street from SR 5/US 1 to west of SR A1A Project

Financial Number: 447672-1-52-01

Project Length: 0.885 miles

Project Limits: State Road (SR) 844/NE 14th Street from SR 5/US 1 to west of SR A1A

Start Date: Fall 2024

Completion Date: Fall 2025

Estimated Construction Cost: $1.8 million

Scope of Work:

  • Repaving the existing roadway
  • Upgrading non-compliant sidewalk ramps
  • Upgrading pedestrian signal features and pedestrian lighting at 2 signalized intersections:
    • US 1
    • NE 23rd Avenue
  • Adding a new signalized pedestrian mid-block crossing on SR 844 at NE 28th Avenue

Construction Impacts:

  • Work will be performed primarily during daytime hours
  • Work will be done in phases to reduce the effects of construction on the community
  • Access to properties adjacent to the corridor will be maintained throughout construction
  • Bicycle traffic will be maintained using shared lane markings
  • Pedestrian detours will be provided to maintain connectivity

Documents:

PDF IconMeeting Invitation and Project Presentation

Point of Contact:

Project Location Map

 
 
 
Please click on a link below to view construction projects
in other areas of Broward County:
I-95 Palm Beach CountyInterstates Northern Palm Beach CountyNortheast Western Palm Beach CountyNorthwest
I-95 Palm Beach CountySoutheast Northern Palm Beach CountySouthwest
Florida Department of Transportation
Florida Department of Transportation
Florida 511 Travel Info
FDOT District Four Youtube
SunGuide
Kids Zone
75 Express
95 Express