US1 Drainage Improvement Project

Posted on 10/30/09
This project was Final Accepted by the Florida Department of Transportation on Saturday, October 24, 2009.

 

Posted on 10/23/09
This project is complete and awaiting Final Acceptance from the Florida Department of Transportation.

 

Posted on 10/16/09
There will be intermittent closures on northbound and southbound U.S. 1, 8 p.m. until 6 a.m., Monday, October 19, to restripe the roadway.  The contractor is still working on various punch-list items to prepare for Final Acceptance from the Florida Department of Transportation.

 

Posted on 10/09/09
There may be intermittent closures on northbound and southbound U.S. 1, 8 a.m. until 4 p.m., while the contractor completes various punch-list items to prepare for Final Acceptance from the Florida Department of Transportation.

This project is nearing completion.

 

 

Posted on 10/02/09
There may be intermittent closures on northbound and southbound U.S. 1, 8 a.m. until 4 p.m., while the contractor completes various punch-list items to prepare for Final Acceptance from the Florida Department of Transportation.

This project is nearing completion.

 

Posted on 09/25/09
There may be intermittent closures on northbound and southbound U.S. 1, 8 a.m.
until 4 p.m. while the contractor completes various punch-list items to prepare for Final
Acceptance from the Florida Department of Transportation.

This project is nearing completion.

 

Posted on 09/18/09
There will be intermittent lane closures on northbound and southbound U.S. 1, Sunday, September 20, through Friday, September 25.  One lane will remain open at all times.

Electronic message boards on U.S. 1 and S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) provide motorists with advance warning. 

 

Posted on 09/11/09
Two northbound and two southbound lanes are now open on U.S. 1. The inside
median and turn lanes will remain closed until approximately Friday, September 18.

There will be intermittent lane closures on northbound and southbound U.S. 1, 8 a.m. until 4
p.m., Monday, September 14, through Friday, September 18, for median repairs.

There will be intermittent closures of northbound and southbound U.S. 1, nightly from 8 p.m.
until 6 a.m., Monday, September 14, through Wednesday, September 16, for final paving
operations. One lane in each direction will remain open at all times. The driveways on S.R. A1A (Jack Nicklaus Drive) will also be paved at this time. One lane will remain open at all times. Flaggers will be on-site to assist motorists. Motorists should anticipate delays.

All businesses on U.S. 1 are open and accessible.

Electronic message boards on U.S. 1 and S.R. A1A / PGA Boulevard (Jack Nicklaus Drive)
provide motorists with advance warning. Motorists should anticipate minimal delays and use caution.

Posted on 09/04/09
Two northbound and two southbound lanes are now open on U.S. 1.  The inside median and turn lanes will remain closed. 

There will be intermittent closures to the inside travel lanes of northbound and southbound U.S.  1, 8 a.m. until 4 p.m., Tuesday, September 8, through Sunday, September 13. This operation will open the northbound left turn lane into Limoncello, the southbound left turn lane into Oakbrook Square and all left turn lanes from Oakbrook Square onto southbound U.S. 1.

There will be one lane closed in each direction on northbound and southbound U.S. 1, 8 a.m. until 4 p.m., Monday, September 14, through Thursday, September 17, for final paving operations.  The driveways on S.R. A1A (Jack Nicklaus Drive) will also be paved at this time. One lane will remain open at all times.  Flaggers will be on-site to assist motorists. Motorists should anticipate delays.

All businesses on U.S. 1 are open and accessible.

Electronic message boards on U.S. 1 and S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) provide motorists with advance warning.  Motorists should anticipate minimal delays and use caution.

 

Posted on 08/28/09
There will be intermittent closures to the inside and outside travel lanes of both northbound and southbound U.S. 1, on Monday, August 31 and Tuesday, September 1, for paving operations and roadway repairs.  One lane will remain open at all times.  Flaggers will be on-site to assist motorists.

There be intermittent closures to the driveways on S.R. A1A (Jack Nicklaus Drive); Hidden Key, Oakbrook Square’s Delivery Driveway and Oakbrook Square’s west entrance and to the left turn lanes onto northbound U.S. 1 at the intersection of PGA Boulevard / S.R. A1A (Jack Nicklaus Drive) on Monday, August 31, for paving operations.  One lane will remain open at all times.  Flaggers will be on-site to assist motorists.

Two northbound and two southbound lanes will be open on U.S. 1, Wednesday, September 2 or Thursday, September 3.  The inside median and turn lanes will remain closed. 

There will be intermittent closures to the inside travel lanes of northbound and southbound U.S.  1, Thursday, September 3 and / or Friday, September 4. The northbound left turn lane into Limoncello and the southbound left turn lane into Oakbrook Square will reopen.  All left turn lanes from Oakbrook Square will be open.

All businesses on U.S. 1 are open and accessible.

Phase Three, which includes all project-related work scheduled for the southbound side of the road, is expected to be completed mid-September 2009.  Electronic message boards on U.S. 1 and S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) provide motorists with advance warning.  Motorists should anticipate minimal delays and use caution.

 

Posted on 08/21/09
U.S. 1 is in the Phase 3B configuration. All directional turn lanes at the intersection of U.S. 1 and PGA Boulevard / S.R. A1A (Jack Nicklaus Drive) and all northbound travel lanes are now open. Southbound U.S. 1 is restricted to one lane on the southbound side of the roadway. 

The entrances to Oakbrook Square from U.S. 1 are open; however, motorists cannot exit the driveway and turn left (south) onto U.S. 1.  All businesses along southbound U.S. 1 are open.

Phase Three, which includes all project-related work scheduled for the southbound side of the road, is expected to be completed in fall 2009.  Electronic message boards on U.S. 1 and S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) provide motorists with advance warning.  Motorists should anticipate minimal delays and use caution.

 

Posted on 08/14/09
U.S. 1 is in the Phase 3B configuration. All directional turn lanes at the intersection of U.S. 1 and PGA Boulevard / S.R. A1A (Jack Nicklaus Drive) and all northbound travel lanes are now open. Southbound U.S. 1 is restricted to one lane on the southbound side of the roadway. 

The entrances to Oakbrook Square from U.S. 1 are open; however, motorists cannot exit the driveway and turn left (south) onto U.S. 1.  All businesses along southbound U.S. 1 are open.

Phase Three, which includes all project-related work scheduled for the southbound side of the road, is expected to be completed in fall 2009.  Electronic message boards on U.S. 1 and S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) provide motorists with advance warning.  Motorists should anticipate minimal delays and use caution.  

 

Posted on 08/07/09

U.S. 1 is in the Phase 3B configuration. All directional turn lanes at the
intersection of U.S. 1 and PGA Boulevard / S.R. A1A (Jack Nicklaus Drive) and all northbound travel lanes are now open. Southbound U.S. 1 is restricted to one lane on the southbound side of the roadway.

The entrances to Oakbrook Square from U.S. 1 are open; however, motorists cannot exit the
driveway and turn left (south) onto U.S. 1. All businesses along southbound U.S. 1 are
open.

Phase Three, which includes all project-related work scheduled for the southbound side of the road, is expected to be completed in fall 2009. Electronic message boards on U.S. 1 and S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) provide motorists with advance warning. Motorists should anticipate minimal delays and use caution.

 

Posted on 07/31/09
U.S. 1 is in the Phase 3B configuration. All directional turn lanes at the intersection of U.S. 1 and PGA Boulevard / S.R. A1A (Jack Nicklaus Drive) and all (two) northbound travel lanes are now open. Southbound U.S. 1 is still restricted to one lane, and is now located on the southbound side of the roadway.

The entrances to Oakbrook Square from U.S. 1 are open; however, motorists cannot exit the driveway and turn left (south) onto U.S. 1. The entrance to Citi Bank off southbound U.S. 1 (Smith Drive) is now open. All businesses alongsouthbound U.S. 1 are open. All southbound travel lanes on U.S. 1, just north of S.R. A1A (Jack Nicklaus Drive) / PGA Boulevard, will be closed from 8 p.m., Sunday, August 2 until 6 a.m., Monday, August 3, for drainage work. Southbound motorists will be detoured westbound along Holman Road, just north of the Melting Pot Plaza, onto southbound Ellison Wilson Road, eastbound to PGA Boulevard and back onto southbound U.S. 1.

Northbound U.S. 1 will be unaffected. There will be no restrictions for motorists at the intersection of U.S. 1 and S.R. A1A (Jack Nicklaus Drive) / PGA Boulevard. Southbound motorists trying to access businesses on the northbound (east) side of U.S. 1 are encouraged to take the approved detour route and travel northbound on U.S. 1. Self Storage, Car Sales of the Palm Beaches / U-haul, Limoncello, Oaktree Plaza, Smith Drive, Universal Pottery and Citi Bank, will be inaccessible during this time. The detour route will be marked with appropriate signage. If the work cannot be completed on this night, the work and
closure will be rescheduled for the evening of Monday, August 4.

Phase Three, which includes all project-related work scheduled for the southbound side of the road, is expected to last until fall 2009, weather permitting. Electronic message boards on U.S. 1 and S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) provide motorists with advance warning. Motorists should anticipate delays and use caution.

 

Posted on 07/24/09
U.S. 1 is in the Phase 3B configuration. All directional turn lanes at the intersection of U.S. 1 and PGA Boulevard / S.R. A1A (Jack Nicklaus Drive) and all (two) northbound travel lanes are now open. Southbound U.S. 1 is still restricted to one lane, and is now located on the southbound side of the roadway.

The entrances to Oakbrook Square from U.S. 1 are open; however, motorists cannot exit the driveway and turn left (south) onto U.S. 1. The entrance to Citi Bank off southbound U.S. 1 (Smith Drive) is now open. All businesses along southbound U.S. 1 are open.

All southbound travel lanes on U.S. 1, just north of S.R. A1A (Jack Nicklaus Drive) / PGA Boulevard, will be closed from 8 p.m., Sunday, August 2 until 6 a.m., Monday, August 3, for drainage work. Southbound motorists will be detoured westbound along Wheeler Road and / or Holman Road, just north of the Melting Pot Plaza, onto southbound Ellison Wilson Road, eastbound to PGA Boulevard and back onto southbound U.S. 1. Northbound U.S. 1 will be unaffected. There will be no restrictions for motorists at the intersection of U.S. 1 and S.R. A1A (Jack Nicklaus Drive) / PGA Boulevard. Southbound motorists trying to access businesses on the northbound (east) side of U.S. 1 are encouraged to take the approved detour route and travel northbound on U.S. 1. Self Storage, Car Sales of the Palm Beaches / U-haul, Limoncello, Oaktree Plaza, Smith Drive, Universal Pottery and Citi Bank, will be
inaccessible during this time. The detour route will be marked with appropriate signage. If the work cannot be completed on this night, the work and closure will be rescheduled for the evening of Monday, August 4.

Phase Three, which includes all project-related work scheduled for the southbound side of the road, is expected to last until fall 2009, weather permitting. Electronic message boards on U.S. 1 and S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) provide motorists with advance warning. Motorists should anticipate delays and use caution.

 

Posted on 07/17/09
U.S. 1 is in the Phase 3B configuration.  All directional turn lanes at the intersection of U.S. 1 and PGA Boulevard / S.R. A1A (Jack Nicklaus Drive) and all (two) northbound travel lanes are now open.  Southbound U.S. 1 is still restricted to one lane, and is now located on the southbound side of the roadway. 

The entrances to Oakbrook Square from U.S. 1 are open; however, motorists cannot exit the driveway and turn left (south) onto U.S. 1.  The entrance to Citi Bank off southbound U.S. 1 (Smith Drive) is now open.  All businesses along southbound U.S. 1 are open.

The driveway to Car Sales of the Palm Beaches / U-Haul will be closed from 4 a.m. until 8 a.m., Tuesday, July 21 and Wednesday, July 22, and the driveway to Self Storage will be closed from 4 a.m. until 8 a.m., Thursday, July 23 and Friday, July 24, for drainage work.  Motorists will not be able to enter or exit these driveways during these times.  These driveways will re-open during business hours.

Phase Three includes all project-related work scheduled for the southbound side of the road and is expected to last until fall 2009, weather permitting.  Electronic message boards on U.S. 1 and S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) provide motorists with advance warning.  Motorists should anticipate delays and use caution.

 

 

Posted on 07/10/09
Southbound traffic is shifted onto a single northbound lane, as part of Phase 3A of construction. There is one lane open in each direction on the northbound side of the road. Only one lane will serve southbound through traffic as well as motorists who want to turn right onto PGA Boulevard / S.R. A1A (Jack Nicklaus Drive), left turns are Friday, July 10, 2009 not be permitted. All business accesses on northbound and southbound U.S. 1 will be open, excluding Citi Bank, (Bomar Drive) located at the northwest corner of PGA Boulevard / S.R. A1A (Jack Nicklaus) and U.S. 1. Motorists will be asked to enter / exit Citi Bank from the driveways located on PGA Boulevard.

The outside left turn lane from eastbound PGA Boulevard onto northbound U.S. 1 and the northbound through lane on U.S. 1 at the intersection of PGA Boulevard / S.R. A1A (Jack Nicklaus Drive) are closed. Northbound motorists will be shifted to the outside right turn lane, which will serve as a through / right turn lane. Northbound left turn lanes onto westbound PGA Boulevard will be unaffected.

The Oakbrook Square entrances off northbound U.S. 1 are now open. Motorists are still unable to travel southbound on U.S. 1 as they leave Oakbrook Square; only right hand turns are permitted.

The traffic shift from Phase 3A to Phase 3B is anticipated to take place nightly, 7 p.m. until 5 a.m., Sunday, July 12, through Tuesday, July 14, weather and unforeseen delays permitting. Phase 3B will open two northbound travel lanes and all directional turn lanes and through lanes at the intersection of U.S. 1 and PGA Boulevard / S.R. A1A (Jack Nicklaus Drive). One southbound through lane and all directional turn lanes on southbound U.S. 1 will be open.

The following driveways will need to be closed to install underground drainage pipe. Dates are pending, however it will not be until sometime on or after July 20; Limoncello Italian Restaurant, Car Sales of the Palm Beaches / U-haul, and Self Storage. These closures will be coordinated directly with the business owner(s) and will take place during non-business hours.

Electronic message boards have been placed on northbound and southbound U. S. 1 and S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) to provide advance warning to motorists forPhase Three construction. Motorists should anticipate delays when traveling southbound through this area and should use caution.

Phase Three includes all project-related work scheduled for the southbound side of the road and is expected to last until fall 2009, weather permitting.

*All businesses along the Westside of U.S. 1 are open.

 

Posted on 07/02/09
Southbound traffic is shifted onto a single northbound lane, as part of Phase 3A of construction. There is one lane open in each direction on the northbound side of the road. Only one lane will serve southbound through traffic as well as motorists who want to turn right onto PGA Boulevard / S.R. A1A (Jack Nicklaus Drive), left turns are not be permitted. All business accesses on northbound and southbound U.S. 1 will be open, excluding Citi Bank, (Bomar Drive) on the northwest corner of PGA Boulevard / S.R. A1A (Jack Nicklaus) and U.S. 1. Motorists will be asked to enter / exit Citi Bank from the driveways located on PGA Boulevard.

The outside left turn lane from eastbound PGA Boulevard onto northbound U.S. 1 and the northbound through lane on U.S. 1 at the intersection of PGA Boulevard / S.R. A1A (Jack Nicklaus Drive) are closed. Northbound motorists will be shifted to the outside right turn lane, which will serve as a through / right turn lane. Northbound left turn lanes onto
westbound PGA Boulevard will be unaffected. This traffic pattern will remain until early July, weather and unforeseen conditions permitting. The contractor will then move to Phase 3B of construction, which will include a new traffic pattern.


The Oakbrook Square entrances off northbound U.S. 1 are now open. Motorists are still unable to travel southbound on U.S. 1 as they leave Oakbrook Square; only right hand turns are permitted.


From 9 p.m. until 5 a.m., nightly, Sunday, July 5, through Tuesday, July 7, the driveway to Oaktree Plaza will be closed all motorists. Motorists will be directed to use Smith Drive, just south of the Oaktree Plaza driveway. This driveway will be reopened during non-working hours. The following driveway closure dates are pending, however it will not be until sometime after July 13; Limoncello Italian Restaurant , Car Sales of the Palm Beaches / U-haul and Self Storage.


The traffic shift from Phase 3A to 3B is anticipated to take place the week of July 13, over three nights, weather and unforeseen delays permitting. Phase 3B will open two northbound travel lanes and all directional turn lanes and through lanes at the intersection of U.S. 1 and PGA Boulevard / S.R. A1A (Jack Nicklaus Drive). One southbound
through lane and all directional turn lanes will be open.


Electronic message boards have been placed on northbound and southbound U. S. 1 and S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) to provide advance warning to motorists for Phase Three construction. Motorists should anticipate delays when traveling southbound through this area and should use caution.

Phase Three includes all project-related work scheduled for the southbound side of the road and is expected to last until fall 2009, weather permitting.

During the week of July 20, Seacoast Utility Authority is anticipating to close southbound U.S.1, for two to three nights, weather permitting. This is operation is being performed by Seacoast Utility Authority and is not part of this projects scope of work. For more information on this closure, please call (561) 627-2900.


*All businesses along the Westside of U.S. 1 are open.

 

Posted on 06/26/09
Southbound traffic is shifted onto a single northbound lane, as part of Phase 3A of construction. There is one lane open in each direction on the northbound side of the road. Only one lane will serve southbound through traffic as well as motorists who want to turn right onto PGA Boulevard / S.R. A1A (Jack Nicklaus Drive), left turns are not be permitted. All business accesses on northbound and southbound U.S. 1 will be open, excluding Citi Bank, (Bomar Drive) on the northwest corner of PGA Boulevard / S.R. A1A (Jack Nicklaus) and U.S. 1.  Motorists will be asked to enter / exit Citi Bank from the driveways located on PGA Boulevard.

The outside left turn lane from eastbound PGA Boulevard onto northbound U.S. 1 and the northbound through lane on U.S. 1 at the intersection of PGA Boulevard / S.R. A1A (Jack Nicklaus Drive) are closed. Northbound motorists will be shifted to the outside right turn lane, which will serve as a through / right turn lane.  Northbound left turn lanes onto westbound PGA Boulevard will be unaffected. This traffic pattern will remain until early July, weather and unforeseen conditions permitting. The contractor will then move to Phase 3B of construction, which will include a new traffic pattern. 

The Oakbrook Square entrances off northbound U.S. 1 are now open.  Motorists are still unable to travel southbound on U.S. 1 as they leave Oakbrook Square; only right hand turns are permitted.

From 10 p.m. until 5 a.m., nightly, Tuesday, June 30 through Thursday, July 2, the driveway to Oaktree Plaza will be closed all motorists.  Motorists will be directed to use Smith Drive, just south of the Oaktree Plaza driveway.   This driveway will be reopened during non-working hours.  The following driveway closure dates are pending, however it will not be until sometime after July 4; Limoncello Italian Restaurant, Car Sales of the Palm Beaches / U-haul and Self Storage. 

Electronic message boards have been placed on northbound and southbound U. S. 1 and S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) to provide advance warning to motorists for Phase Three construction.  Motorists should anticipate delays when traveling southbound through this area and should use caution.  

Phase Three includes all project-related work scheduled for the southbound side of the road and is expected to last until fall 2009, weather permitting.

*All businesses along the Westside of U.S. 1 are open. 

 

 

Posted on 06/19/09
Southbound traffic is shifted onto a single northbound lane, as part of Phase 3A of construction. There is one lane open in each direction on the northbound side of the road. Only one lane will serve southbound through traffic as well as motorists who want to turn right onto PGA Boulevard / S.R. A1A (Jack Nicklaus Drive), left turns are not be permitted. All business accesses on northbound and southbound U.S. 1 will be open, excluding Citi Bank, (Bomar Drive) on the northwest corner of PGA Boulevard / S.R. A1A (Jack Nicklaus) and U.S. 1.  Motorists will be asked to enter / exit Citi Bank from the driveways located on PGA Boulevard.
 
The outside left turn lane from eastbound PGA Boulevard onto northbound U.S. 1 and the northbound through lane on U.S. 1 at the intersection of PGA Boulevard / S.R. A1A (Jack Nicklaus Drive) are closed. Northbound motorists will be shifted to the outside right turn lane, which will serve as a through / right turn lane.  Northbound left turn lanes onto westbound PGA Boulevard will be unaffected. This traffic pattern will remain until the end of June, weather and unforeseen conditions permitting. The contractor will then move to Phase 3B of construction, which will include a new traffic pattern.
 
The Oakbrook Square entrances off northbound U.S. 1 are now open.  Motorists are still unable to travel southbound on U.S. 1 as they leave Oakbrook Square; only right hand turns are permitted.
 
On 8 a.m. Monday, June 22, through 7 p.m., Tuesday, June 23, Smith Drive will be closed to all motorists. Motorists will be directed to use the Oaktree Plaza entrance / exit off southbound U.S. 1. Weather permitting, this closure is anticipated to last two full days, however, the driveway will be reopened as soon as the work is completed. Electronic message boards will alert motorists of the alternate route.


From 10 p.m. until 5 a.m., nightly, Wednesday, July 1 and Thursday, July 2, the driveway to Oaktree Plaza will be closed all motorists. Motorists will be directed to use Smith Drive, just south of the Oaktree Plaza driveway.  This driveway will be reopened during non-working hours. The following driveway closure dates are pending, however it will not be until sometime after July 4; Limoncello Italian Restaurant, Car Sales of the Palm Beaches / U-haul and Self Storage.


Electronic message boards have been placed on northbound and southbound U. S. 1 and S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) to provide advance warning to motorists for Phase Three construction. Motorists should anticipate delays when traveling southbound through this area and should use caution.  
 
Phase Three includes all project-related work scheduled for the southbound side of the road and is expected to last until fall 2009, weather permitting.
 
*All businesses along the Westside of U.S. 1 are open.

 

Posted on 06/12/09
Southbound traffic is shifted onto a single northbound lane, as part of Phase 3A of construction. There will be one lane open in each direction on the northbound side of the road. Only one lane will serve southbound through traffic as well as motorists who want to turn right onto PGA Boulevard / S.R. A1A (Jack Nicklaus Drive), left turns are not be permitted. All business entrances on northbound and southbound U.S. 1 will be open, excluding Citi Bank, (Bomar Drive) on the northwest corner of PGA Boulevard / S.R. A1A (Jack Nicklaus) and U.S. 1.  Motorists will be asked to enter / exit Citi Bank from the driveways located on PGA Boulevard.

The outside left turn lane from eastbound PGA Boulevard onto northbound U.S. 1 and the northbound through lane on U.S. 1 at the intersection of PGA Boulevard / S.R. A1A (Jack Nicklaus Drive) are closed. Northbound motorists will be shifted to the outside right turn lane, which will serve as a through / right turn lane.  Northbound left turn lanes onto westbound PGA Boulevard will be unaffected. This traffic pattern will remain until the end of June, weather and unforeseen conditions permitting. The contractor will then move to Phase 3B of construction, which will include a new traffic pattern. 

The Oakbrook Square entrances off northbound U.S. 1 are now open.  Motorists are still unable to travel southbound on U.S. 1 as they leave Oakbrook Square; only right hand turns are permitted.

The week of June 22 (an exact date has not been determined), Smith Drive will be closed for approximately two days, weather permitting.  Motorists will be detoured through Oaktree Plaza.  Electronic message boards will guide motorists. 

Electronic message boards have been placed on northbound and southbound U. S. 1 and S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) to provide advance warning to motorists for Phase Three construction.  Motorists should anticipate delays when traveling southbound through this area and should use caution.  

Phase Three includes all project-related work scheduled for the southbound side of the road and is expected to last until fall 2009, weather permitting.

*All businesses along the Westside of U.S. 1 are open.

Posted on 06/05/09
Southbound traffic is shifted onto a single northbound lane, as part of Phase 3A of
construction. There will be one lane open in each direction on the northbound side of the road. Only one lane will serve southbound through traffic as well as motorists who want to turn right onto PGA Boulevard / S.R. A1A (Jack Nicklaus Drive), left turns are not be permitted. All business entrances on northbound and southbound U.S. 1 will be open, excluding Citi Bank, (Bomar Drive) on the northwest corner of PGA Boulevard / S.R. A1A (Jack Nicklaus) and U.S. 1. Motorists will be asked to enter / exit Citi Bank from the driveways located on PGA Boulevard.

The outside left turn lane from eastbound PGA Boulevard onto northbound U.S. 1 and the northbound through lane on U.S. 1 at the intersection of PGA Boulevard / S.R. A1A (Jack Nicklaus Drive) are closed. Northbound motorists will be shifted to the outside right turn lane, which will serve as a through / right turn lane. Northbound left turn lanes onto westbound PGA Boulevard will be unaffected. This traffic pattern will remain for approximately three weeks, weather / unforeseen conditions permitting. The contractor will then move to Phase 3B of construction, which will include a new traffic pattern.

The Oakbrook Square entrance off U.S. 1 is now open.

Electronic message boards have been placed on northbound and southbound U. S. 1 and S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) to provide advance warning to motorists for Phase Three construction. Motorists should anticipate delays when traveling southbound through this area and should use caution.

Phase Three includes all project-related work scheduled for the southbound side of the road and is expected to last until fall 2009, weather permitting.


*All businesses along the Westside of U.S. 1 are open.

 

 

Posted on 05/29/09
Northbound and southbound traffic is restricted to one lane in each direction on the southbound side of U. S. 1 until approximately Sunday, May 31, weather permitting.  The inside left turn lane of southbound U.S. 1 onto S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) and the outside left turn lane of eastbound PGA Boulevard onto northbound U.S. 1 are closed.  The northbound through/right turn lane on U.S. 1 turning onto S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) is now a right-turn only lane.

The Oakbrook Square exit off and entrance off U.S. 1 will be closed until Monday, June 1, due to weather delays.  Motorists are asked to enter and exit the plaza through the two northern driveways on U.S. 1 (Golden Bear Plaza and Stein Mart) or the southern driveways on S.R. A1A / PGA Boulevard (Jack Nicklaus Drive), until that time.

Weather permitting, at 8 p.m., Sunday, May 31, northbound lanes will reopen and southbound traffic will be shifted onto a single northbound lane. There will be one lane open in each direction on the northbound side of the road. Only one lane will serve southbound through traffic as well as motorists who want to turn right onto PGA Boulevard / S.R. A1A (Jack Nicklaus Drive), left turns will not be permitted. All business entrances on northbound and southbound U.S. 1 will be open, excluding Citi Bank, (Bomar Drive) on the northwest corner of PGA Boulevard / S.R. A1A (Jack Nicklaus) and U.S. 1.  Motorists will be asked to enter / exit Citi Bank from the driveways located on PGA Boulevard.

The outside left turn lane from eastbound PGA Boulevard onto northbound U.S. 1 and the northbound through lane on U.S. 1 at the intersection of PGA Boulevard / S.R. A1A (Jack Nicklaus Drive) will also be closed. Northbound motorists will be shifted to the outside right turn lane, which will serve as a through / right turn lane.  Northbound left turn lanes onto westbound PGA Boulevard will be unaffected. This traffic pattern will remain for approximately three weeks. If the traffic shift cannot be completed on this night, the work and closure will be rescheduled for the following evening, weather permitting, until the work is complete.

Electronic message boards have been placed on northbound and southbound U. S. 1 and S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) to provide advance warning to motorists for Phase Three construction.  Motorists should anticipate delays when traveling through this area and should use caution.  
Phase Two includes all project-related work scheduled for the northbound side of the road.  Phase Three includes all project-related work scheduled for the southbound side of the road and is expected to last until fall 2009, weather permitting.

*All businesses along this corridor are open.

 

Posted on 05/22/09
This 0.18 mile drainage improvement project in the City of Palm Beach Gardens began on January 12, 2009. This project includes installing new storm water drainage outside of the roadway; repaving; utility work and the installation of French drainage. This project will be constructed in phases to minimize impacts to the public.   This $2.19 million project is being performed by Ranger Construction Industries and is expected to be complete late October 2009

Northbound and southbound traffic is restricted to one lane in each direction on the southbound side of U. S. 1 until approximately Wednesday, May 26, weather permitting.  The inside left turn lane of southbound U.S. 1 onto S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) and the outside left turn lane of eastbound PGA Boulevard onto northbound U.S. 1 are closed.  The northbound through/right turn lane on U.S. 1 turning onto S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) is now a right-turn only lane.

The Oakbrook Square exit off and entrance off U.S. 1 will be closed until Wednesday, May 27.  Motorists are asked to enter and exit the plaza through the two northern driveways on U.S. 1 (Golden Bear Plaza and SteinMart) or the southern driveways on S.R. A1A / PGA Boulevard (Jack Nicklaus Drive), until that time.

Beginning at 8 p.m. on Tuesday, May 26, northbound lanes will reopen and southbound traffic will be shifted onto a single northbound lane. There will be one lane open in each direction on the northbound side of the road. Only one lane will serve southbound through traffic as well as motorists who want to turn right onto PGA Boulevard / S.R. A1A (Jack Nicklaus Drive), left turns will not be permitted. All business entrances on northbound and southbound U.S. 1 will be open, excluding Citi Bank, (Bomar Drive) on the northwest corner of PGA Boulevard / S.R. A1A (Jack Nicklaus) and U.S. 1.  Motorists will be asked to enter / exit Citi Bank from the driveways located on PGA Boulevard.

The outside left turn lane from eastbound PGA Boulevard onto northbound U.S. 1 and the northbound through lane on U.S. 1 at the intersection of PGA Boulevard / S.R. A1A (Jack Nicklaus Drive) will also be closed. Northbound motorists will be shifted to the outside right turn lane, which will serve as a through / right turn lane.  Northbound left turn lanes onto westbound PGA Boulevard will be unaffected. This traffic pattern will remain for approximately three weeks.

Electronic message boards have been placed on northbound and southbound U. S. 1 and S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) to provide advance warning to motorists for Phase Three construction.  Motorists should anticipate delays when traveling through this area and should use caution.  
Phase Two includes all project-related work scheduled for the northbound side of the road.  Phase Three includes all project-related work scheduled for the southbound side of the road and is expected to last until fall 2009, weather permitting.

*All businesses along this corridor are open. 

 

Posted on 05/15/09
Northbound and southbound traffic is restricted to one lane in each direction on the
southbound side of U. S. 1 until approximately Friday, May 22, weather permitting. The inside left turn lane of southbound U.S. 1 onto S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) and the outside left turn lane of eastbound PGA Boulevard onto northbound U.S. 1 are closed. The northbound through/right turn lane on U.S. 1 turning onto S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) is now a right-turn only lane.

The Oakbrook Square exit off and entrance off U.S. 1 will be closed until Friday, May 22. Motorists are asked to enter and exit the plaza through the two northern driveways on U.S. 1 (Golden Bear Plaza and SteinMart) or the southern driveways on S.R. A1A / PGA Boulevard (Jack Nicklaus Drive), until that time.

Beginning at 8 p.m., Thursday, May 21, the contractor will shift traffic for Phase Three of construction. Northbound lanes will reopen and southbound traffic will be shifted onto a single northbound lane. There will be one lane open in each direction on the northbound side of the road. One lane will serve southbound through traffic as well as motorists who want to turn left or right onto PGA Boulevard / S.R. A1A (Jack Nicklaus Drive). All business entrances on northbound and southbound U.S. 1 will be open, excluding Citi Bank on the northwest corner of PGA Boulevard / S.R. A1A (Jack Nicklaus) and U.S. 1. Motorists will be asked to enter / exit Citi Bank from the driveways located on PGA Boulevard.

The outside left turn lane from eastbound PGA Boulevard onto northbound U.S. 1 and the northbound through lane on U.S. 1 at the intersection of PGA Boulevard / S.R. A1A (Jack Nicklaus Drive) will also be closed. Northbound motorists will be shifted to the outside right turn lane, which will serve as a through / right turn lane. Northbound left turn lanes onto westbound PGA Boulevard will be unaffected. This traffic pattern will remain for approximately two weeks.

Electronic message boards have been placed on northbound and southbound U. S. 1 and S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) to provide advance warning to motorists for Phase Three construction. Motorists should anticipate delays when traveling through this area and should use caution.

Phase Two includes all project-related work scheduled for the northbound side of the road. Phase Three includes all project-related work scheduled for the southbound side of the road and is expected to last until fall 2009, weather permitting

*All businesses along this corridor are open. Access to businesses will be maintained throughout construction

Posted on 05/08/09
Northbound and southbound traffic is restricted to one lane in each direction on the
southbound side of U. S. 1 until approximately June 2009, weather permitting. The inside left turn lane of southbound U.S. 1 onto S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) and the outside left turn lane of Friday, May 08, 2009 eastbound PGA Boulevard onto northbound U.S. 1 are closed. The northbound through/right turn lane on U.S. 1 turning onto S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) is now a right-turn only lane.

The Oakbrook Square exit off northbound U.S. 1 will be closed during this phase of construction and the entrance will be closed until late May 2009. Motorists are asked to enter and exit the plaza through the two northern driveways on U.S. 1 (Golden Bear Plaza and SteinMart) or the southern driveways on S.R. A1A / PGA Boulevard (Jack Nicklaus Drive).

Electronic message boards have been placed on northbound and southbound U. S. 1 and S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) to provide advance warning to motorists for Phase Two construction. Motorists should anticipate delays when traveling through this area and should use caution.

Phase Two includes all project-related work scheduled for the northbound side of the road.

 

Posted on 05/01/09
Northbound and southbound traffic is restricted to one lane in each direction on the southbound side of U. S. 1 until approximately June 2009, weather permitting.  The inside left turn lane of southbound U.S. 1 onto S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) and the outside left turn lane of eastbound PGA Boulevard onto northbound U.S. 1 are closed.  The northbound through/right turn lane on U.S. 1 turning onto S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) is now a right-turn only lane.

The Oakbrook Square exit off northbound U.S. 1 will be closed during this phase of construction and the entrance will be closed until late May 2009.  Motorists are asked to enter and exit the plaza through the two northern driveways on U.S. 1 (Golden Bear Plaza and SteinMart) or the southern driveways on S.R. A1A / PGA Boulevard (Jack Nicklaus Drive).

Electronic message boards have been placed on northbound and southbound U. S. 1 and S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) to provide advance warning to motorists for Phase Two construction.  Motorists should anticipate delays when traveling through this area and should use caution.  
Phase Two includes all project-related work scheduled for the northbound side of the road.

*All businesses along this corridor are open and access to businesses will be maintained throughout construction.

 

Posted on 04/24/09
Northbound and southbound traffic is restricted to one lane in each direction on the
southbound side of U. S. 1 until approximately June 2009, weather permitting. The inside left turn lane of southbound U.S. 1 onto S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) and the outside left turn lane of eastbound PGA Boulevard onto northbound U.S. 1 are closed. The northbound through/right turn lane on U.S. 1 turning onto S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) is now a right-turn only lane.

The Oakbrook Square exit off northbound U.S. 1 will be closed during this phase of construction and the entrance will be closed until May 2009. Motorists are asked to enter and exit the plaza through the two northern driveways on U.S. 1 (Golden Bear Plaza and SteinMart) or the southern driveways on S.R. A1A / PGA Boulevard (Jack Nicklaus Drive). Electronic message boards will guide motorists to alternate entrance / exit locations.

Electronic message boards have been placed on northbound and southbound U. S. 1 and S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) to provide advance warning to motorists for Phase Two construction. Motorists should anticipate delays when traveling through this area and should use caution.

Phase Two includes all project-related work scheduled for the northbound side of the road.

*All businesses along this corridor are open and access to businesses will be maintained throughout construction.

 

Posted on 04/17/09
Northbound and southbound traffic is restricted to one lane in each direction on the southbound side of U. S. 1 until approximately June 2009, weather permitting.  The inside left turn lane of southbound U.S. 1 onto S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) and the outside left turn lane of eastbound PGA Boulevard onto northbound U.S. 1 are closed.  The northbound through/right turn lane on U.S. 1 turning onto S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) is now a right-turn only lane.

The Oakbrook Square exit off northbound U.S. 1 will be closed during this phase of construction and the entrance will be closed until May 2009.  Motorists are asked to enter and exit the plaza through the two northern driveways on U.S. 1 or the southern driveways on S.R. A1A / PGA Boulevard (Jack Nicklaus Drive). Electronic message boards will guide motorists to alternate entrance / exit locations.

Electronic message boards have been placed on northbound and southbound U. S. 1 and S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) to provide advance warning to motorists for Phase Two construction.  Motorists should anticipate delays when traveling through this area and should use caution.  

Phase Two includes all project-related work scheduled for the northbound side of the road.

Posted on 04/10/09
Northbound and southbound traffic is restricted to one lane in each direction on the southbound side of U. S. 1 until approximately June 2009, weather permitting. The inside left turn lane of southbound U.S. 1 onto S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) and the outside left turn lane of eastbound PGA Boulevard onto northbound U.S. 1 are closed. The northbound through/right turn lane onU.S. 1 turning onto S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) is now a right-turn only lane.

The Oakbrook Square exit off northbound U.S. 1 will be closed during this phase of construction and the entrance will be closed from Tuesday, April 7, through May 2009. Motorists are asked to enter and exit the plaza through the two northern driveways on U.S. 1 or the southern driveways on S.R. A1A / PGA Boulevard (Jack Nicklaus Drive). Electronic message boards will guide motorists to alternate entrance / exit locations.

Electronic message boards have been placed on northbound and southbound U. S. 1 and S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) to provide advance warning to motorists for Phase Two construction. Motorists should anticipate delays when traveling through this area and should use caution.

Phase Two includes all project-related work scheduled for the northbound side of the road.
*All businesses along this corridor are open and access to businesses will be maintained
throughout construction.

Please log on to the project Web site for information on Phase Two construction
www.pbfdot.com/95Expansion.

Posted on 04/03/09
Northbound and southbound traffic is restricted to one lane in each direction on the
southbound side of U. S. 1 until approximately June 2009, weather permitting. The inside left turn lane of southbound U.S. 1 onto S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) and the outside left turn lane of eastbound PGA Boulevard onto northbound U.S. 1 are closed. The northbound through/right turn lane on U.S. 1 turning onto S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) is now a right-turn only lane.

The Oakbrook Square exit off northbound U.S. 1 will be closed during this phase of construction and the entrance will be closed from Tuesday, April 7, through Sunday, April 12. Motorists are asked to enter and exit the plaza through the two northern driveways on U.S. 1 or the southern driveways on S.R. A1A / PGA Boulevard (Jack Nicklaus Drive). Electronic message boards will guide motorists to alternate entrance / exit locations.

Electronic message boards have been placed on northbound and southbound U. S. 1 and S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) to provide advance warning to motorists for Phase Two construction. Motorists should anticipate delays when traveling through this area and should use caution.

Phase Two includes all project-related work scheduled for the northbound side of the road.

Posted on 03/27/09
Northbound and southbound traffic is restricted to one lane in each direction on the southbound side of U. S. 1 for approximately three months, weather permitting.  The inside left turn lane of southbound U.S. 1 onto S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) and the outside left turn lane of eastbound PGA Boulevard onto northbound U.S. 1 are closed.  The northbound through/right turn lane on U.S. 1 turning onto S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) is now a right-turn only lane.
 
The Oakbrook Square exit off northbound U.S. 1 will be closed during this phase of construction.  There will be intermittent closures to this entrance.  Motorists are asked to enter and exit the plaza through the two northern entrances on U.S. 1 or the southern entrances on S.R. A1A / PGA Boulevard (Jack Nicklaus Drive).

Electronic message boards have been placed on northbound and southbound U. S. 1 and S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) to provide advance warning to motorists for Phase Two construction.  Motorists should anticipate delays when traveling through this area and should use caution.  

Phase Two includes all project-related work scheduled for the northbound side of the road.

Posted on 03/20/09
Northbound and southbound traffic is restricted to one lane in each direction on the southbound side of U. S. 1 for approximately three months, weather permitting. The inside left turn lane of southbound U.S. 1 onto S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) and the outside left turn lane of eastbound PGA Boulevard onto northbound U.S. 1 are closed. The northbound through/right turn lane on U.S. 1 turning onto S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) is a right-turn only lane. The lanes have been closed during this phase of construction for installation of drainage pipes, French drains and utility lines.

The exit located in the center of Oakbrook Square to northbound U.S. 1 has been closed during this phase of construction. There will be intermittent closures to this entrance. Motorists are asked to enter and exit the plaza through the two northern entrances on U.S. 1 or the southern entrances on S.R. A1A / PGA Boulevard (Jack Nicklaus Drive).

Electronic message boards have been placed on northbound and southbound U. S. 1 and S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) to provide advance warning to motorists for Phase Two construction. Motorists should anticipate delays when traveling through this area and should use caution.

Phase Two includes all project-related work scheduled for the northbound side of the road.

Posted on 03/13/09
Northbound and southbound traffic is restricted to one lane in each direction and northbound traffic is being rerouted onto the southbound side of U. S. 1, for approximately three months, weather permitting.  The inside left turn lane of southbound U.S. 1 onto S.R. A1A/ PGA Boulevard (Jack Nicklaus Drive) and the outside left turn lane of eastbound PGA Boulevard onto northbound U.S. 1 are closed.  The northbound through/right turn lane on U.S. 1 onto S.R. A1A (Jack Nicklaus Drive) is now a right-turn only.
 
The main Oakbrook Square exit off northbound U.S. 1 is now closed.  Motorists leaving Oakbrook Square must use the exits available on the north side or south side of the plaza. There will be no southbound access onto U.S. 1; motorists must use the exit on S.R. A1A.

Electronic message boards have been placed on northbound and southbound U. S. 1 and S.R. A1A/ PGA Boulevard (Jack Nicklaus Drive) to provide advance warning to motorists entering the construction area.  Motorists should anticipate delays when traveling through this area and should use caution.

Posted on 03/06/09
The inside left turn lane on southbound U.S. 1 to turn onto S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) will be closed, 9 a.m. until 1 p.m., Monday, March 9, for survey operations.

Beginning at 7 p.m., Tuesday, March 7, contractors will begin installing barrier wall to prepare for a traffic shift that will begin at 7 a.m., Wednesday, March 8. The shift will close all northbound lanes of U.S. 1 at S.R. A1A / PGA Boulevard (Jack Nicklaus Drive), and move northbound traffic over to the southbound side of the road to begin Phase Two. The inside left turn lane of southbound U.S. 1 onto S.R. A1A/ PGA Boulevard (Jack Nicklaus Drive) and the outside left turn lane of eastbound PGA Boulevard onto northbound U.S. 1 will also be closed. There will be one lane open in each direction through the work zone for the duration of this phase, which will last approximately three months, weather and unforeseen circumstances permitting.

The Oakbrook Square entrance off northbound U.S. 1 will be closed during this phase of construction. Motorists will be asked to enter the plaza through the southern entrance on S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) or the northern entrances on U.S. 1. Phase Two includes all project-related work scheduled for the northbound side of the road. Electronic message boards will be on-site to direct motorists to the plaza entrances.

Electronic message boards have also been placed on northbound and southbound U. S. 1 and S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) to provide advance warning to motorists. Motorists should anticipate delays when traveling through this area and should use caution.

Phase Two includes all project-related work scheduled for the northbound side of the road.

Posted on 02/27/09
Repaving of the driveways to the Hidden Key Community, Oakbrook Square’s west entrance off S.R. A1A/PGA Boulevard and the delivery access is scheduled from 9 a.m. until 6 p.m., Monday, March 2, and Tuesday, March 3. There will be alternating lane closures to each of the driveways. A flagger will be on site to direct traffic. Driveways will reopen during non-working hours.

Electronic message boards have been placed on northbound and southbound U. S. 1 and S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) to provide advance warning to motorists for Phase Two construction, which will begin in early March 2009. Motorists should anticipate delays when traveling through this area and should use caution.

The Phase Two traffic shift is tentatively schedule for the night of Tuesday, March 10, 2009. During this phase, northbound lanes will be closed completely and all northbound traffic will be shifted on one lane on the southbound side of U.S. 1. The inside left turn lane of southbound U.S. 1 onto S.R. A1A/ PGA Boulevard (Jack Nicklaus Drive)
and the outside left turn lane of eastbound PGA Boulevard onto northbound U.S. 1 will be closed during this phase, which will last approximately three months, weather permitting.

The Oakbrook Square entrance off northbound U.S. 1 will be closed during this phase of construction. Motorists will be asked to enter the plaza through the two northern entrances on U.S. 1 or on S.R. A1A/ PGA Boulevard (Jack Nicklaus Drive).

Phase Two includes all project-related work scheduled for the northbound side of the road.

Posted on 02/20/09
All lanes to the Oakbrook Square delivery access off S.R. A1A/ PGA Boulevard (Jack Nicklaus Drive) will be closed, 6 p.m. until 7 a.m., *Sunday, February 15 and Monday, February 16, 2009.  This driveway will be closed to all traffic during these times. Motorists are being asked to use the Oakbrook Square entrance off S.R. A1A/ PGA Boulevard or U.S. 1.  This driveway will be reopened during non-working hours.

All lanes to the west entrance of Oakbrook Square off S.R. A1A/ PGA Boulevard (Jack Nicklaus Drive) will be closed, 6 p.m. until 7 a.m., *Tuesday, February 17 and Wednesday, February 18, 2009.  This driveway will be closed to all traffic during these times. Motorists are being asked to use the Oakbrook Square entrances off S.R. A1A/ PGA Boulevard or U.S. 1.  The driveway will be reopened during non-working hours.

*The contractor anticipates each location taking two nights to complete. However, if they finish a drainage crossing at any location in one night, they will move to the following location the next night.

Posted on 02/13/09
All lanes to the Oakbrook Square delivery access off S.R. A1A/ PGA Boulevard (Jack Nicklaus Drive) will be closed, 6 p.m. until 7 a.m., *Sunday, February 15 and Monday, February 16, 2009.  This driveway will be closed to all traffic during these times. Motorists are being asked to use the Oakbrook Square entrance off S.R. A1A/ PGA Boulevard or U.S. 1.  This driveway will be reopened during non-working hours.

All lanes to the west entrance of Oakbrook Square off S.R. A1A/ PGA Boulevard (Jack Nicklaus Drive) will be closed, 6 p.m. until 7 a.m., *Tuesday, February 17 and Wednesday, February 18, 2009.  This driveway will be closed to all traffic during these times. Motorists are being asked to use the Oakbrook Square entrances off S.R. A1A/ PGA Boulevard or U.S. 1.  The driveway will be reopened during non-working hours.

*The contractor anticipates each location taking two nights to complete. However, if they finish a drainage crossing at any location in one night, they will move to the following location the next night.

Posted on 02/06/09
There will be temporary lane closures to the entrance/exit of the Hidden Key Community off S.R. A1A/ PGA Boulevard (Jack Nicklaus Drive), 8 a.m. until 6 p.m., Monday, February 9 and Tuesday, February 10, 2009.  One lane will remain open at all times.  Flaggers will be on-site to assist motorists entering and exiting the community.  Two-way traffic will be restored during non-working hours.

All lanes to the Oakbrook Square delivery access off S.R. A1A/ PGA Boulevard (Jack Nicklaus Drive) will be closed, 6 p.m. until 7 a.m., Sunday, February 15 and Monday, February 16, 2009.  This driveway will be closed to all traffic during these times. Motorists are being asked to use the Oakbrook Square entrance off S.R. A1A/ PGA Boulevard or U.S. 1.  This driveway will be reopened during non-working hours.

All lanes to the west entrance of Oakbrook Square off S.R. A1A/ PGA Boulevard (Jack Nicklaus Drive) will be closed, 6 p.m. until 7 a.m., Tuesday, February 17 and Wednesday, February 18, 2009.  This driveway will be closed to all traffic during these times. Motorists are being asked to use the Oakbrook Square entrances off S.R. A1A/ PGA Boulevard or U.S. 1.  The driveway will be reopened during non-working hours.

Posted on 01/23/09
There are no closures at this time.

Posted on 01/16/09
There will be a single lane closure on westbound S.R. A1A/ PGA Blvd. (Jack Nicklaus Dr.), from the Little Lake Worth Canal to U.S. 1, 9 a.m. until 6 p.m., Monday, January 19 through Thursday, January 22, to relocate pedestrian paths.

Posted on 01/09/09
There will be a single lane closure on westbound S.R. A1A/ PGA Blvd. (Jack Nicklaus Dr.), from U.S. 1 to the Little Lake Worth Canal, 8 a.m. until 6 p.m., Monday, January 12 through Friday, January 16, to relocate pedestrian paths.

Posted on 01/02/09
There are no restrictions at this time. Phase One began on Monday, January 5, on S.R. A1A/ PGA Blvd.

Posted on 12/12/08
There will be an Informational Open House held from 8 a.m. until 5 p.m., Wednesday, December 17, 2008. This is an informal meeting and project personnel will be available to answer questions and address concerns. Motorists, businesses and residents are encouraged to attend.

Posted on 11/26/08
There will be an Informational Open House held from 8 a.m. until 5 p.m., Wednesday, December 17. This is an informal meeting and project personnel will be available to answer questions and address concerns. Motorists, businesses and residents are encouraged to attend.

Posted on 11/21/08
There will be an Informational Open House held from 8 a.m. until 5 p.m., Wednesday, December 17. This is an informal meeting and project personnel will be available to answer questions and address concerns. Motorists, businesses and residents are encouraged to attend.

Posted on 11/14/08
There will be an Informational Open House held from 5 p.m. until 7 p.m., Wednesday, November 19 and 8 a.m. until 5 p.m., Wednesday, December 17. This is an informal meeting and project personnel will be available to answer questions and address concerns. Motorists, businesses and residents are encouraged to attend.

Posted on 11/07/08
There will be an Informational Open House held on Wednesday, November 19 from 5 p.m. until 7 p.m. and on Wednesday, December 17 from 8 a.m. until 5 p.m.  This is an informal meeting and project personnel will be available to answer questions and address concerns.

PROJECT PROGRESS

Posted on 02/27/09
This week the contractor expects to finish installing the new sidewalk along the north side of State Road A1A / PGA Boulevard (Jack Nicklaus Drive).  They will also begin installing landscaping and sod along the route, as Phase One of the project comes to an end.  The final paving operations in the Phase One area will not take place until October 2009.  
 
The contractor began preliminary work for Phase Two of construction, Monday, February 23.  The concrete median was removed and the area is now paved to get ready for the future traffic shift.
 
Phase Two includes all project-related work scheduled for the northbound side of the road.  During this phase, northbound lanes will be closed completely and all northbound traffic will be shifted on one lane on the southbound side of U.S. 1. The inside left turn lane of southbound U.S. 1 onto eastbound S.R. A1A/ PGA Boulevard (Jack Nicklaus Drive) and the outside left turn lane of eastbound PGA Boulevard onto northbound U.S. 1 will be closed during this phase, which will last approximately three months, weather permitting.

The Oakbrook Square entrance off northbound U.S. 1 will be closed during this phase of construction.  Motorists will be asked to enter the plaza through the two northern entrances on U.S. 1 or on S.R. A1A/ PGA Boulevard (Jack Nicklaus Drive).

Electronic message boards have been placed on northbound and southbound U. S. 1 and S.R. A1A / PGA Boulevard (Jack Nicklaus Drive) to provide advance warning to motorists.  Motorists should anticipate delays when traveling through this area and should use caution.

Posted on 02/06/09
This week the contractor will continue installing drainage pipe and running dewatering pumps. Dewatering will keep the trenches dry as the contractor continues to excavate and install drainage pipe.  

Beginning on Monday, February 9, 2009, the contractor will begin installing Phase One drainage pipe along S.R. A1A/ PGA Boulevard (Jack Nicklaus Drive). In order to perform this work safely, it will be necessary to close driveways temporarily at Hidden Key, Oakbrook Square delivery access and Oakbrook Square’s west entrance off S.R. A1A/ PGA Boulevard. Closures are scheduled as follows: (Please note that this schedule is tentative and is subject to change due to weather or other unforeseen circumstances.)

Hidden Key Community - 8 a.m. until 6 p.m., Monday, February 9 and Tuesday, February 10, 2009.  One lane will remain open at all times.  Flaggers will be on-site to assist motorists entering and exiting the community.  Two-way traffic will be restored during non-working hours.

Oakbrook Square delivery access – 6 p.m. until 7 a.m., Sunday, February 15 and Monday, February 16, 2009.  This driveway will be closed to all traffic. Motorists are being asked to use the Oakbrook Square entrances off S.R. A1A/ PGA Boulevard or U.S. 1.  This driveway will be reopened during non-working hours.

Oakbrook Square, west entrance off S.R. A1A/ PGA Boulevard – 6 p.m. until 7 a.m., Tuesday, February 17 and Wednesday, February 18, 2009.  This driveway will be closed to all traffic. Motorists are being asked to use the Oakbrook Square entrances off S.R. A1A/ PGA Boulevard or U.S. 1.  The driveway will reopen during non-working hours.

U.S. 1 (S.R. 5) at S.R. A1A/PGA Boulevard
Drainage Improvement Project

Posted on 01/30/09
Pedestrian paths have been relocated to the south. The delivery access to Oakbrook Square is now open.
 
Beginning on Sunday, January 25, the contractor will begin dewatering their work site.  This will keep the trenches dry as the contractor begins to excavate and install pipe.  
 
On Wednesday, January 28, Seacoast will begin to relocate their water main and force main.