Complete

SR 706 / Indiantown Road

Description
This project includes: milling and resurfacing, rebuilding shoulders, improving signals, installing irrigation, enhancing medians and landscaping.

Start Date
June 16, 2008

Completion
Early 2009

Project Length
1.5 miles

Cost
$2.4 million

Final Acceptance
December 26, 2008

Project Team

FDOT Senior Project Administrator
Scott Burrie

FDOT Project Administrator
Roxanne Riggs

Contractor
Hubbard Construction Company

Public Information Officer
Alicia De Fago
561-718-4709
95info@pbfdot.com

Press Release
Mast Arm