I-95 (PGA Boulevard to Donald Ross Road)
Description
This project includes continuing the HOV lane, widening 2.9 miles of existing interstate to 10 lanes (five in each direction), and installing new signs, signalization, lighting and landscaping.
Start Date
September 14, 2008
Completion
Spring 2012
Project Length
4.3 miles
Cost
$44.8 million
Project Team
FDOT Construction Project Manager
Scott Burrie
CCEI Senior Project Engineer
Michael Irwin, P.E., TBE Group
Contractor
Community Asphalt Corporation
Public Information Officer
Peter Dobens
561-718-4709
[email protected]