State Road (SR) 729/State Market Road Resurfacing, Restoration and Rehabilitation Project

Financial Number: 446105-1-52-01

Project Length: 2.272 miles

Project Limits: State Road (SR) 729/State Market from south of SR 717/Muck City Road to SR 15/US 441/E Main Street

Start Date: April 28, 2024

Completion Date: Spring 2025

Contractor: Halley Engineering Contractors, Inc.

Estimated Construction Cost: $4.9 million

Scope of Work: Project improvements include milling and resurfacing SR 729/State Market Road, widening traffic lanes from 11 feet to 12 feet, widening the existing paved shoulders as permitted by FDOT right-of-way, reconstructing northbound SR 729/State Market Road sidewalks and shared use paths from north of Rock Pit Road to SR 15/US 441/E Main Street and upgrading signage and pavement markings throughout project limits.

Contact Information:

Para información y preguntas en Español, por favor llame al (954) 777-4302.

Documents:

PDF IconFULL CLOSURE SR 729_Sept 2024 to Dec 2024_082724.pdf

PDF IconFULL CLOSURE SR 729_May 1 to Sept 30 2024

PDF IconSR 729 Market Road Project Flyer



 

Project Photos

Pre-Construction

Click to view enlarged version/details
20240307_155619 20240307_155818 20240307_16000420240307_160300
20240307_160343 20240307_160644 20240307_160723 20240307_161031

During Construction

Click to view enlarged version/details
SR 729 NB Silt Fence Installation   May 2024 Delivery of Equipment an Materials to Staging Area   May 2024 SR 729 Milling Existing Travel Lanes and Shoulders   June 2024 SR 729 NB Silt Fence Installation and Clearing and Grubbing   June 2024
NB SR 729 shoulder widening and base material placement   July 2024 NB SR 729 shoulder widening and geogrid material placement   July 2024 SR 729 SB Shoulder Widening _ Subbase Material Placement   August 2024 SR 729 SB Shoulder Widening _Filter Fabric Material Placement   August 2024
SR 729 SB and NB New Pavement from Muck City Road to Larrimore Road   September 2024 Sod placement on slopes   September 2024 SR 729 SB and NB Milled Surface   October 2024 SR 729 Northbound Geogrid Material placement   October 2024
Clearing and Grubbing Along the East Side of Military Trail South of Forest Hill Blvd   October 2024 NB SR 729 base material placement after shoulder widening   November 2024NB SR 729 base material primed after shoulder widening   November 2024
 

Please click on a link below to view construction projects
in other areas of Palm Beach County:
  I-95 Palm Beach CountyI-95 Construction Palm Beach County Northern Palm Beach CountyNorthern Palm Beach County
  Southern Palm Beach CountySouthern Palm Beach County Western Palm Beach CountyWestern Palm Beach County
  Central Palm Beach CountyCentral Palm Beach County Bridges Palm Beach CountyBridge Construction Palm Beach County

Florida Department of Transportation
Florida Department of Transportation
FDOT District Four Youtube
Kids Zone
zero