Financial Number: 447663-1-52-01
Project Length: 2.074 Miles
Project Limits: State Road (SR) A1A/South Ocean Boulevard from south of Lake Avenue to north of Ibis Way
Project Purpose: : The Resurfacing, Restoration and Rehabilitation (RRR) project will extend the service life of the pavement, enhance roadway safety, and improve operating characteristics of the corridor.
A Public Meeting: Thursday, June 15, 2023, at 6:00 p.m. The public meeting will be conducted both in-person and virtually
The in-person public meeting will take place at the Tideline Ocean Resort located at 2842 South Ocean Boulevard, Palm Beach, FL 33480, and doors will open at 5:30 p.m.
To participate in the virtual public meeting, please use the following link to register: https://tinyurl.com/447663-1-SRA1A.
If using a mobile device, the free “GoToWebinar” application will be required to attend. If you prefer to dial in by phone, call +1 (951) 384-3421 and then dial the Audio Access code: 940-173-356.
Start Date: Fall 2024
Completion Date: Late 2025
Estimated Construction Cost: $3.5 Million
Scope of Work:
- Repave the existing roadway
- Widen the paved shoulder to 5-feet
- Replace the existing 5-foot asphalt sidewalk with a 6-foot concrete sidewalk
- Upgrade pedestrian curb ramps to meet with Americans with Disabilities Act (ADA) standards
- Upgrade signing and pavement markings
- Upgrade lighting, and pedestrian signals at Lake Avenue, at the mid-block crossing of Raymond Floyd Golf Course, and at Phipps Ocean Park
- Improve drainage as needed
Construction Impacts:
- Work will be done in phases to reduce the effects of construction on the community
- Temporary lane closures will be required during daytime hours:
- Monday – Friday from 8:00 AM to 4:00 PM
- Access to businesses and residences will be maintained at all times
- No detours are necessary
Contact Information:
|