FDOT District Four - Palm Beach Header Image

Current Maintenance, Utility and Permit Closures in Palm Beach County

Jan 15 - Jan 22, 2020

Traffic Impact: Belvedere Road under I-95, in West Palm Beach, may have a moving intermittent lane closure operation, 9 p.m. to 5 a.m., Sunday night through Thursday morning, for roadway striping. For more information, please contact Paul Watt at 954-380-0895.

Traffic Impact: I-95 may have a moving lane closure operation, with intermittent lane closures in each direction as needed, 12 p.m. until 5 a.m. Monday night, and 9 p.m. until 5 a.m., Tuesday night through Thursday night, for sign installation operations. For more information, please contact Paul Watt at 954-380-0895.

Traffic Impact: Southbound I-95 beginning at the exit ramp to 6th Avenue, in Lake Worth, 9 a.m. until 3:30 p.m., Monday through Friday, through Thursday, Feb. 4, 1 of 2 lanes closed, for maintenance work. For more information, please contact Erwin Mosqueda at 561-985-4270.

Traffic Impact: Advanced notice—The entrance and exit ramps/bridges to the Palm Beach International Airport (PBIA), as well as at the I-95/Belvedere Road and Australian Avenue entrance and exit ramps/bridges in the vicinity of PBIA, in West Palm Beach, may have intermittent single lane and shoulder closures as needed, 9 a.m. until 4 p.m., Monday, Jan. 25, through Friday, Jan. 29, for inspection operations. The inspections will be a moving operation; all three locations will not have lane closures simultaneously. For more information, please contact Jose Quintana at (305) 342-2620.

Traffic Impact: Advanced notice—STRIDE (Statewide Traffic and Railroad Initiative emphasizing Dynamic Envelopes) Improvements Project, installing high emphasis pavement markings to warn drivers and pedestrians to stay clear of the South Florida Rail Corridor (SFRC) and CSX Railroad (RR) tracks. The contractor will be working at one crossing at a time, weather permitting, at the SFRC tracks in Palm Beach County. Ocean Avenue in Boynton Beach, Lake Ida Road and NW 17 Ave. in Lake Worth, SW 10th Street and Congress Avenue in Delray Beach, may have up to two lanes closed in each direction, nightly, 10 p.m. until 5 a.m., Sunday night, Jan. 31, through Friday morning, Feb. 5. Palmetto Park Road and Military Trail, Camino Real Road, and SW 18th Street and SW 17th Street, in Boca Raton, may have up to two lanes closed in each direction, nightly, 10 p.m. until 5 a.m., Sunday night, Feb. 7, through Friday morning, Feb. 12. For more information, please contact Erick Rojo at 305-494-3249.

Traffic Impact: Brightline Construction, Jupiter – Railroad Crossing at Toney Penna Dr. Full road closure, 7 a.m., Monday, January 18 through 7 p.m., Thursday, January 28.

Detour Information:

Eastbound Toney Penna Dr. traffic wishing to access Alternate A1A will be directed to travel north on Military Trail to Indiantown Rd., travel east on Indiantown Rd. to Alternate A1A and travel south on Alternate A1A.

Alternate A1A traffic wishing to travel west on Toney Penna Dr. will be directed to travel north on Alternate A1A to Indiantown Rd., travel west on Indiantown Rd. to Military Trail and travel south on Military Trail to access Toney Penna Dr.

Southbound Old Dixie Hwy. traffic wishing to access Alternate A1A will be directed to travel east on Indiantown Rd. to Alternate A1A.

Northbound Old Dixie Hwy. traffic will be directed to travel west on Jupiter Lakes Blvd. to Military Trail, travel north on Military Trail to Indiantown Rd. and travel east on Indiantown Rd. to access Old Dixie Hwy. For more information, please contact Katie Mitzner at 407-502-3587.

Traffic Impact: Brightline Construction, West Palm Beach – Railroad Crossing at 36th St. Full road closure, 7 a.m., Monday, January 25 through 7 p.m., Friday, February 5.

Detour Information:

Eastbound 36th St. traffic will be directed to travel south on Greenwood Ave. to 30th St., travel east on 30th St to Pinewood Ave. and travel north on Pinewood Ave. to access 36th St.

Westbound 36th St. traffic will be directed to travel south on Pinewood Ave. to 30th St., travel west on 30th St. to Greenwood Ave. and travel north on Greenwood Ave. to access 36th St. For more information, please contact Katie Mitzner at 407-502-3587.

Traffic Impact: Brightline Construction, Jupiter – Railroad Crossing at Center St.

Full road closure, 7 a.m., Thursday, February 11 through 7 p.m., Wednesday, February 20.

Detour Information:

Eastbound Center St. traffic will be directed to travel south on N. Loxahatchee Dr. to W. Indiantown Rd., travel east on W. Indiantown Rd. to Alternate A1A and travel north on Alternate A1A to access Center St.

Westbound Center St. traffic will be directed to travel south on Alternate A1A to W. Indiantown Rd., travel west on W. Indiantown Rd. to N. Loxahatchee Dr. and travel north on N. Loxahatchee Dr. to access Center St. For more information, please contact Katie Mitzner at 407-502-3587.

Traffic Impact: Brightline Construction, Palm Beach Gardens – Railroad Crossing at Donald Ross Rd. Full road closure, through 7 p.m., Sunday, January 17.

Detour Information:

Eastbound Donald Ross Rd. traffic will be directed to travel north on Military Trail to Frederick Small Rd., travel east on Frederick Small Rd. to Alternate A1A/Old Dixie Hwy. and travel south on Alternate A1A/Old Dixie Hwy. to access Donald Ross Rd.

Westbound Donald Ross Rd. traffic will be directed to travel north on Alternate A1A/Old Dixie Hwy. to Frederick Small Rd., travel west on Frederick Small Rd. to Military Trail and travel south on Military Trail to access Donald Ross Rd.

Southbound Alternate A1A/Old Dixie Hwy. traffic wishing to travel west on Donald Ross Rd. will be directed to travel west on Frederick Small Rd. to Military Trail and travel south on Military Trail to access Donald Ross Rd.

Northbound Alternate A1A/Old Dixie Hwy. wishing to travel west on Donald Ross Rd. will be directed to travel west on Hood Rd. to Military Trail and travel north on Military Trail to access Donald Ross. Rd. For more information, please contact Katie Mitzner at 407-502-3587.

Traffic Impact: Florida’s Turnpike, Northbound and southbound Florida’s Turnpike/SR 91 exit ramps to Glades Road/SR 808 (Exit 75) Overnight full ramp closures, 9 p.m. to 5 a.m., Monday, January 18, and nightly through Thursday, January 21.

Detour Information:

Northbound Florida’s Turnpike/SR 91 traffic wishing to access Glades Road/SR 808 (Exit 75) will be directed to exit at Sample Road/SR 834 (Exit 69), travel east on Sample Road to Powerline Road/SR 845 and travel north on Powerline Road to access Glades Road.

Southbound Florida’s Turnpike/SR 91 traffic wishing to access Glades Road/SR 808 (Exit 75) will be directed to exit at Atlantic Avenue/SR 806 (Exit 81), travel west on Atlantic Avenue to US 441/SR 7 and travel south on US 441 to access Glades Road. For more information, please contact Fiorella Teodista at 954-663-0612.

Traffic Impact: Florida’s Turnpike, Northbound and southbound Florida’s Turnpike/SR 91 entrance ramps from Glades Road/SR 808. Overnight full ramp closures, 9 p.m. to 5 a.m., Monday, January 18, and nightly through Thursday, January 21.

Detour Information:

Eastbound and westbound Glades Road/SR 808 traffic wishing to access northbound Florida’s Turnpike/SR 91 will be directed to US 441/SR 7, travel north on US 441 to Atlantic Avenue/SR 806 and travel east on Atlantic Avenue to access northbound Florida’s Turnpike.

Eastbound and westbound Glades Road/SR 808 traffic wishing to access southbound Florida’s Turnpike/SR 91 will be directed to Powerline Road/SR 845, travel south on Powerline Road to Sample Road/SR 834 and travel west on Sample Road to access southbound Florida’s Turnpike. For more information, please contact Fiorella Teodista at 954-663-0612.

Traffic Impact: Florida’s Turnpike, Southbound Florida’s Turnpike/SR 91 entrance ramp from Boynton Beach Boulevard/SR 804. Weekend full ramp closure, 8 p.m. Friday, January 22, to 6 a.m., Monday, January 25.

Detour Information:

Eastbound and westbound Boynton Beach Boulevard/SR 804 traffic wishing to access southbound Florida’s Turnpike/SR 91 will be directed to US 441/SR 7, travel south on US 441 to Atlantic Avenue/SR 806 and travel east on Atlantic Avenue to access southbound Florida’s Turnpike. For more information, please contact Fiorella Teodista at 954-663-0612.

Traffic Impact: Eastbound and westbound Glades Road at Florida’s Turnpike, daytime single lane closure, 9 a.m. to 4 p.m., Tuesday through Friday. Please note this closure will not affect the entrance or exit ramps. For more information, please contact Fiorella Teodista at 954-663-0612.

Traffic Impact: Eastbound and westbound Atlantic Avenue at Florida’s Turnpike, daytime single lane closure, 9 a.m. to 4 p.m., Tuesday through Friday. Please note this closure will not affect the entrance or exit ramps. For more information, please contact Fiorella Teodista at 954-663-0612.

Traffic Impact: Eastbound and westbound Boynton Beach Boulevard at Florida’s Turnpike, daytime single lane closure, 9 a.m. to 4 p.m., Tuesday through Friday, January 8. Please note this closure will not affect the entrance or exit ramps. For more information, please contact Fiorella Teodista at 954-663-0612.

Traffic Impact: Eastbound Lake Worth Road/SR 802 from Cypress Isle Way to Florida’s Turnpike/SR 91, daytime single lane closure, 9 a.m. to 4 p.m., Tuesday, through Friday. For more information, please contact Fiorella Teodista at 954-663-0612.

Traffic Impact: Northbound North Federal Highway between Southeast 9 Street and Southeast 7 Street, in Boca Raton, 9 a.m. until 3:30 p.m., Monday through Friday, through Friday, Feb. 12, 2021, 1 of 3 lanes closed, for concrete pouring and construction. For more information, please contact Edward van Wingen 561-706-5642, Lance Wayne 786-920-8686 or Carol Judd 786-999-3943.

Traffic Impact: Westbound North Quadrille Boulevard between 6 Street and 5 Street, in West Palm Beach, 9 a.m. until 3:30 p.m., Monday through Friday, through Friday, Jan. 22, 2021, 2 of 2 lanes closed as needed, for electric power path conduit installation. For more information, please contact Daniel Moura 561-418-0598.

Traffic Impact: Westbound Lake Worth Road just East of Congress Avenue, in Lake Worth, 9 a.m. until 3:30 p.m., Monday through Friday, through Friday, Feb. 26, 2021, 1 of 2 lanes closed, for force main repairs. For more information, please contact Frank Kendrix 813-299-6320.

Traffic Impact: Eastbound Glades Road between Northwest 4 Avenue and Northwest 2 Avenue, in Boca Raton, 9 a.m. until 3:30 p.m., Monday through Friday, through Monday, Feb. 8, 2021, 1 of 3 lanes closed, for directional boring and conduit installation. For more information, please contact Daniel Moura 561-418-0598.

Traffic Impact: Eastbound and Westbound Forest Hill Boulevard between Eschleman Trail and Turnpike, in West Palm Beach, 9 a.m. until 3:30 p.m., Monday through Friday, through Friday, Jan. 22, 2021 1 of 3 lanes closed, for directional boring, wood pole and conduit installation. For more information, please contact Daniel Moura 561-418-0598.

Traffic Impact: Southbound North Federal Highway between Lancaster Street and Manchester Street, in Boca Raton, 9 a.m. until 3:30 p.m., Monday through Friday, through Monday, Jan. 25, 2021, 1 of 2 lanes closed, for pole and equipment installation. For more information, please contact Daniel Moura 561-418-0598.

Traffic Impact: Westbound Southern Boulevard between Sansburys Way and Fairground Road, in West Palm Beach, 9 a.m. until 3:30 p.m., Monday through Friday, through Friday, Jan. 29, 2021, 1 of 4 lanes closed, for small cell equipment and concrete pole installations. For more information, please contact Daniel Moura 561-418-0596.

Traffic Impact: Northbound South Federal Highway between Southeast 9 Street and Southeast 7 Street, in Boca Raton, 9 a.m. until 3:30 p.m., Monday through Friday, through Friday, Jan. 29, 2021, 1 of 3 lanes closed, for building material loading delivery. For more information, please contact Carol Judd 786-999-3943.

Traffic Impact: Eastbound Lake Worth Road between Bridgette Road and Southview Road, in Lake Worth, 9 a.m. until 3:30 p.m., Monday through Friday, through Friday, Jan. 29, 2021, 1 of 3 lanes closed, for concrete pole installation. For more information, please contact Ted Howard 954-904-7011 or Robert Mitchell 305-901-9541.

Traffic Impact: Westbound Southwest 10 Street at intersection Southwest 24 Avenue, in Deerfield Beach, 9 a.m. until 3:30 p.m., Monday through Friday, Monday, through Friday, Jan. 22, 2021, 1 of 1 lane closed as needed, for underground facilities installment. For more information, please contact Anna Tupitsyna 954-551-5130.

Traffic Impact: Westbound Lake Worth Road between Jackson Avenue and Bridgette Road, in Lake Worth, 7 p.m. until 5 a.m., Monday through Friday, through Friday, Jan. 29, 2021, 1 of 3 lanes closed, for concrete pole installation. For more information, please contact Ted Howard 954-904-7011 or Robert Mitchell 305-901-9541.

Traffic Impact: Southbound South Dixie Highway between Belvedere Road and Monceaux Road, in West Palm Beach, 9 a.m. until 3:30 p.m., Monday through Friday, through Monday, Feb. 15, 2021, 1 of 2 lane closed, for concrete pole and equipment installation. For more information, please contact Daniel Moura 561-418-0598.

Traffic Impact: Westbound Okeechobee Boulevard between South Sapodilla Avenue and South Rosemary Avenue, in West Palm Beach, 9 a.m. until 3:30 p.m., Monday through Friday, through Tuesday, Feb. 9, 2021, 1 of 4 lanes closed, for directional boring installation. For more information, please contact Daniel Moura 561-418-0596.

Traffic Impact: Eastbound Glades Road at intersection of 95 Avenue, in Boca Raton, 7 p.m. until 5 a.m., Monday through Friday, through Wednesday, Mar. 31, 2021, 2 of 3 lanes closed, for water main installation. For more information, please contact Steven Kopelskopel 954-270-5290.

Traffic Impact: Southbound North Quadrille Boulevard between Banyan Boulevard and 3 Street, in West Palm Beach, 9 a.m. until 3:30 p.m., Monday through Friday, through Wednesday, Feb. 10, 2 of 2 lanes closed as needed, for directional boring, conduit and pole installation. For more information, please contact Daniel Moura 561-418-0598.

Traffic Impact: Southbound North Ocean Drive between Ridge Boulevard and Harbour Drive, in Boynton Beach, 9 a.m. until 3:30 p.m., Monday through Friday, through Friday, Jan. 29, 2021, 2 of 2 lanes closed as needed, for directional boring and conduit installation. For more information, please contact Daniel Moura 561-418-0598.

Traffic Impact: Westbound and eastbound West Indiantown Road, just east of Carver Avenue and just west of Loxahatchee River, in Jupiter, 9 a.m. until 3:30 p.m., Monday through Friday, through Friday, Feb. 26, 2021, 1 of 3 lanes closed, for manholes and conduit system maintenance work. For more information, please contact Sean Linn 772-332-4854.

Traffic Impact: Northbound North Federal Highway between Northeast 70 Street and Northeast 69 Circle, in Boca Raton, 9 a.m. until 3:30 p.m., Monday through Friday, through Friday, Jan. 29, 2021, 1 of 2 lanes closed, for equipment and concrete pole installation. For more information, please contact Daniel Moura 561-418-0596.

Traffic Impact: Northbound North Federal Highway between Northeast 36 Street and Northeast 32 Street, in Boca Raton, 9 a.m. until 3:30 p.m., Monday through Friday, through Friday, Jan. 29, 2021, 1 of 3 lanes closed, for directional boring and conduit installation. For more information, please contact Daniel Moura 561-418-0596.

Traffic Impact: Northbound North Military Trail between Johnson Dairy Road and PGA Boulevard, in Palm Beach Gardens, 9 a.m. until 3:30 p.m., Monday through Friday, through Friday, Feb. 26, 2021, 1 of 3 lanes closed, for manhole and conduit system maintenance. For more information, please contact Sean Linn 772-332-4854.

Traffic Impact: Eastbound and westbound Southern Boulevard and South Ocean Boulevard at around the round-about A1A intersection, in Palm Beach, 7 p.m. until 5 a.m., Monday through Friday, through Friday, Jan. 29, 2021, 1 of 2 lanes closed, for water main and water sampling point installation and patching. For more information, please contact Robert Earnst 561-718-4536.

Traffic Impact: Southbound State Road 7 between North of 92 Place North and South of 72 Place South, in Boynton Beach, 9 a.m. until 3:30 p.m., Monday through Friday, through Monday, Apr. 5, 2021, 1 of 3 lanes closed, for wood and concrete poles replacement and installation. For more information, please contact Art Rodriguez 561-475-0064.

Traffic Impact: Northbound Highway A1A between Old Dixie Highway and Eyeball Avenue, in Jupiter, 9 a.m. until 3:30 p.m., Monday through Friday, through Friday, Feb. 19, 1 of 3 lanes closed, for directional boring installation. For more information, please contact Miguel Arronte 786-479-8190

Traffic Impact: Southbound and Northbound US Highway 1 at intersection of Northlake Boulevard, in North Palm Beach, 8 a.m. until 5 p.m., Monday through Friday, through Friday, Jan. 29, 1 of 2 lanes closed, for water main and sanitary force main construction. For more information, please contact Prajwal Aditya 954-719-5949.

Traffic Impact: Northbound Highway A1A between Ocean Boulevard to Coconut Road, in Jupiter, 9 a.m. until 3:30 p.m., Monday through Friday, through Friday, Jan. 29, 1 of 3 lanes closed, for directional bore installation. For more information, please contact Miguel Arronte 786-479-8190.

Traffic Impact: Southbound North Federal Highway to East Boynton Beach, in Boynton Beach, 9 a.m. until 3:30 p.m., Monday through Friday, through Friday, Feb. 19, 1 of 2 lanes closed, for directional boring and conduit installation. For more information, please contact Miguel Arronte 786-479-8190.

Traffic Impact: Westbound West Ocean Avenue between Northwest 3 Street and Northwest 7 Street, in Boynton Beach, 9 a.m. until 3:30 p.m., Monday through Friday, through Friday, Feb. 19, 1 of 2 lanes closed, for directional boring and conduit installation. For more information, please contact Miguel Arronte 786-479-8190.

Traffic Impact: Eastbound Forest Hill Boulevard between Pine Tree Lane and Norton Avenue, in West Palm Beach, 9 a.m. until 3:30 p.m., Monday through Friday, through Friday, Feb. 19, 1 of 3 lanes closed, for directional boring and conduit installation. For more information, please contact Miguel Arronte 786-479-8190.

Traffic Impact: Northbound North Military Trail between just North of Blue Heron Boulevard and just south of Woods Edge Circle, in Riviera Beach, 9 a.m. until 3:30 p.m., through Friday Jan. 22, 1 of 3 lanes closed, for removal of existing curb, driveway and sidewalk and curb, driveway and sidewalk installation. For more information, please contact Lynne Holden 954-325-8582.

Traffic Impact: Eastbound Yamato Road between North West Boca Raton Boulevard and North Dixie Highway, in Boca Raton, 9 a.m. until 3:30 p.m., Monday through Friday, through Friday, Feb. 26, 1 of 3 lanes closed, for directional boring and conduit installation. For more information, please contact Antonio Seco 954-529-5029 or 305-803-9769.

Traffic Impact: Northbound North Military Trail between Kent Avenue and Purdy Lane, in West Palm Beach, 9 a.m. until 3:30 p.m., Monday through Friday, through Friday, Apr. 9, 1 of 3 lanes closed, for concrete poles installation. For more information, please contact Maryann Green 561-495-7608.

Traffic Impact: Northbound South Congress Avenue between Kentucky Avenue and Shawnee Road, in West Palm Beach, 9 a.m. until 3:30 p.m., Monday through Friday, through Friday, Mar. 19, 1 of 3 lanes closed, for wooden pole removal and installation. For more information, please contact Latess Hill 561-631-0663.

Traffic Impact: Southbound Florida State Road A1A between East Ocean Avenue and Golfview Drive, in Lantana, 9 a.m. until 3:30 p.m., Monday through Friday, through Friday, Jan. 29, 1 of 2 lane closed, for driveway connection. For more information, please contact Billy Jenkins 305-505-4008.

Traffic Impact: Westbound Bee Line Highway/State Road 710 between PGA Boulevard and North Palm Beach County General Airport, in West Palm Beach, 8 p.m. until 5 a.m., Monday through Friday through Friday, Feb. 19, 1 of 2 lanes closed, for insulators replacements. For more information, please contact Craig Couglin 561-603-9381.

Traffic Impact: Southbound State Road 7 between Sandalfoot Boulevard and Boca Entrada Boulevard, in Boca Raton, 9 a.m. until 3:30 p.m., Monday through Friday, through Friday, Jan. 29, 1 of 3 lanes, for wooden pole installation and maintenance at facilities. For more information, please contact Ted Howard 954-907-4011 or Robert Mitchell 305-901-9541.

Traffic Impact: Westbound Lake Worth Road between Hadjes Drive and 480’ ft West of Cindy Lane, in Lake Worth, 9 a.m. until 3:30 p.m., Monday through Friday, Friday, Jan. 22 through Friday, Feb. 12, 1 of 3 lanes closed, for concrete pole installation. For more information, please contact Ted Howard 954-904-7011 or Robert Mitchell 305-901-9541.

Traffic Impact: Westbound Okeechobee Boulevard between South Sapodilla Avenue and South Rosemary Avenue, in West Palm Beach, 9 a.m. until 3:30 p.m., Monday through Friday, through Wednesday, Mar. 31, 1 of 4 lanes closed, for directional boring and conduit installation. For more information, please contact Daniel Moura 561-418-0596.

Traffic Impact: Southbound Highway A1A between East Riverside Drive and Center Street, in Jupiter, 9 a.m. until 5 p.m., Monday through Friday, through Friday, Feb. 26, 1 of 3 lanes closed, for maintenance on existing sewer force main. For more information, please contact Joe Jesteeadt 561-262-0289 and/or Ryan Chernekoff 561-262-3461.

Traffic Impact: Westbound Lake Worth Road between Cypress Edge Drive and State Road 7, in Lake Worth, 8 p.m. until 5 a.m., Monday through Friday, through Friday, Jan. 29, 1 of 3 lanes closed, for pole replacement and maintenance. For more information, please contact Ted Howard 954-904-7011 or Robert Mitchell 305-901-9541.

Traffic Impact: Westbound East Atlantic Avenue between Northeast 7 Avenue and Northeast 6 Avenue, in Delray Beach, 9 a.m. until 3:30 p.m., Monday through Friday, through Friday, Feb. 19, 1 of 2 lanes closed, for apply exterior elements. For more information, please contact Alex Bacallao 954-598-2081.

Traffic Impact: Southbound North Ocean Boulevard Boynton Inlet Pier and Seal Lake Drive, in Boynton Beach, 8 p.m. until 5 a.m., Monday through Friday, Friday, Jan. 22 through Friday, Feb. 26, 1 of 2 lanes closed, for conduit installation. For more information, please contact Daniel Moura 561-418-0596.

Traffic Impact: Southbound South Dixie Highway between Belvedere Road and Monceaux Road, in West Palm Beach, 9 a.m. until 3:30 p.m., Monday through Friday, Tuesday, Jan. 19 through Friday, Mar. 19, 1 of 2 lane closed, for directional boring and conduit installation. For more information, please contact Daniel Moura 561-418-0598.

Florida Department of Transportation
FDOT District Four Youtube
Kids Zone