Financial Number: 449832-1-32-01
Project Length: 0.773 miles
Project Limits:
SR 5/S Federal Highway from US 1/SR 5/N Dixie Highway to 10 Avenue S
Virtual Public Workshop: Wednesday, August 20, 2025, (5:30 p.m. – 7:00 p.m.)
Link to registration page https://attendee.gotowebinar.com/register/1816700420103119712
Projected Letting: July 2026
Start Date: August 2026
Completion Date: May 2027
Estimated Construction Cost: $1.0 M
Scope of Work:
- Repave the existing roadway to improve the resiliency of infrastructure.
- Pavement marking “sharrows” will be added to provide bicycle access.
- Adjust manhole tops and valves.
- Reconstruct damaged sidewalks and pull boxes.
- Upgrade pedestrian curb ramps to add detectible warning surfaces at the following intersections:
- US 1
- 18th Avenue South
- 15th Avenue South
- 14th Avenue South
- 13th Avenue South
- 12th Avenue South
- 11th Avenue South
- 10th Avenue South
Construction Impacts:
- Work will be done in phases to reduce the impacts of construction on the community.
- Temporary lane closures will be done during non-peak hours on non-event days.
- Access to residences and businesses will be maintained during construction.
Contact Information:
Para información y preguntas en Español, por favor llame al (954) 777-4302.
Documents: Southern_Blvd_flier_v8.pdf
|