SR-93/I-75 Improvements Project from SR-822/Sheridan Street to SR-818/Griffin Road

Financial Number: 437832-4-52-01

Project Length: 1.5 miles

Project Limits: SR-93/I-75 from SR-822/Sheridan Street to SR-818/Griffin Road

Start Date: April 2023

Completion Date: Late 2024

Contractor: Halley Engineering Contractors, Inc.

Estimated Construction Cost: $12.7 million

Scope of Work:
The project improvements include roadway widening to provide continuous auxiliary lanes and 10-foot shoulders in each direction of SR-93/I-75, repaving and restriping the existing asphalt, replacing overhead signage, installing new guardrail in each direction of SR-93/ I-75, and updating drainage, lighting, and Intelligent Transportation Systems (ITS).

Point of Contact:

Para información y preguntas en Español, por favor llame al (954) 777-4302.

 

Documents:

PDF IconI-75 SB Full Closure April 1 7

PDF IconProject Flyer

 

Click here for upcoming lane closures

 

Project Photos

Pre-Construction

During Construction

 


Please click on a link below to view construction projects
in other areas of Broward County:
I-95 Palm Beach CountyInterstates Northern Palm Beach CountyNortheast Western Palm Beach CountyNorthwest
I-95 Palm Beach CountySoutheast Northern Palm Beach CountySouthwest
Florida Department of Transportation
Florida Department of Transportation
Florida 511 Travel Info
FDOT District Four Youtube
SunGuide
Kids Zone
75 Express
95 Express