Financial Number: 437832-4-52-01
Project Length: 1.5 miles
Project Limits: SR-93/I-75 from SR-822/Sheridan Street to SR-818/Griffin Road
Virtual Public Meeting: Tuesday, March 21, 2023 from 5 p.m. to 6 p.m. Please use the following link to register: https://tinyurl.com/i75from_sheridanto_griffin or dial into +1 (562) 247-8422, access code: 793-104-939
In-Person Construction Open House: Tuesday, March 21, 2023 from 6 p.m. to 7 p.m. at the Ivanhoe Community Center, located at 6101 Volunteer Road, Davie, FL 33331.
Start Date: April 2023
Completion Date: Spring 2025
Contractor: Halley Engineering Contractors, Inc.
Estimated Construction Cost: $12.7 million
Scope of Work:
The project improvements include roadway widening to provide continuous auxiliary lanes and 10-foot shoulders in each direction of SR-93/I-75, repaving and restriping the existing asphalt, replacing overhead signage, installing new guardrail in each direction of SR-93/ I-75, and updating drainage, lighting, and Intelligent Transportation Systems (ITS).